SCHEDULE 3—INTERCONNECTION PROCESS,TECHNICAL REQUIREMENTS,AND OPERATING PROCEDURES <br /> During this step, the Area EPS shall complete the review of the final Generation System design. <br /> If the final design has significant changes from the Generation System proposed on the original <br /> Application which invalidate the engineering studies or the preliminary engineering screening, the <br /> Generation System Interconnection Application request may be rejected by the Area EPS <br /> Operator and the Applicant may be requested to reapply with the revised design. <br /> Upon completion of this step the Generation Interconnection Coordinator shall supply the <br /> following information to the Applicant. <br /> 1) Requested modifications or corrections of the detailed drawings provided by the <br /> Applicant. <br /> 2) Approval of and mutual agreement with the Project Schedule.(This may need to be <br /> interactively discussed between the Parties,during this Step) <br /> 3) Final review of Distributed Generation Credit amount(s)(where applicable). <br /> 4) Initial testing procedure review comments. (Additional work on the testing process will occur <br /> during Step 8,once the actual equipment is identified) <br /> Step 8 Order Equipment and Construction (By Both Parties) <br /> The following activities shall be completed during this step. For larger installations this step will <br /> involve much interaction between the Parties. It is typical for approval drawings to be supplied by <br /> the Applicant to the Area EPS for review and comments. It is also typical for the Area EPS to <br /> require review and approval of the drawings that cover the interconnection equipment and <br /> interconnection protection system. If the Area EPS also requires remote control and/or <br /> monitoring, those drawings are also exchanged for review and comment. <br /> By the Applicant's personnel: <br /> 1) Ordering of Generation System equipment. <br /> 2) Installing Generation System. <br /> 3) Submit approval drawings for interconnection equipment and protection systems,as <br /> required by Area EPS Operator. <br /> 4) Provide final relay settings provided to the Area EPS Operator. <br /> 5) Submit Completed and signed Engineering Data Submittal form. <br /> 6) Submit proof of insurance,as required by the Area EPS tariff(s)or interconnection <br /> agreements. <br /> 7) Submit required State of Minnesota electrical inspection forms("blue Copy)filedwith the <br /> Area EPS Operator. <br /> 8) Inspecting and functional testing Generation System components. <br /> 9) Work with the Area EPS personnel and equipment vendor(s)to finalize the <br /> installation testing procedure. <br /> By Area EPS personnel: <br /> 1) Ordering any necessary Area EPS equipment. <br /> 2) Installing and testing any required equipment. <br /> a) Monitoring facilities. <br /> b) Dedicated Equipment. <br /> 3) Assisting Applicant's personnel with interconnection installation coordination issues <br /> 4) Providing review and input for testing procedures. <br /> Step 9 Final Tests (By Area EPS /Applicant) <br /> (Due to equipment lead times and construction, a significant amount of time may take place <br /> between the execution of Step 8 and Step 9.) During this time the final test steps are developed <br /> and the construction of the facilities are completed. <br /> Interconnection Process for Distributed Generatiy8 Systems <br />