SCHEDULE 3—INTERCONNECTION PROCESS,TECHNICAL REQUIREMENTS,AND OPERATING PROCEDURES <br /> Step 6 Final Go-No Go Decision (By Applicant) <br /> In this step, the Applicant shall again have the opportunity to indicate whether or not they want to <br /> proceed with the proposed generation interconnection. If the decision is NOT to proceed, the <br /> Applicant will notify the Area EPS Generation Interconnection Coordinator, so that other <br /> generation interconnections in the queue are not adversely impacted. Should the Applicant <br /> decide to proceed, a more detailed design, if not already completed by the Applicant, must be <br /> done, and the following information is to be supplied to the Area EPS Generation Interconnection <br /> Coordinator: <br /> 1) Applicable up-front payment required by the Area EPS,per Payment Schedule, <br /> provided in Step 5.(if applicable) <br /> 2) Signed Interconnection Agreement(if applicable). <br /> 3) Final proposed schedule,incorporating the Area EPS comments.The schedule of the project <br /> should include such milestones as foundations poured,equipment delivery dates,all conduit <br /> installed,cutover(energizing of the new switchgear/transfer switch),Area EPS work, relays <br /> set and tested,preliminary vendor testing,final Area EPS acceptance testing,and any other <br /> major milestones. <br /> 4) Detailed one-line diagram of the Generation System,including the generator,transfer <br /> switch/switchgear,service entrance, lockable and visible disconnect,metering,protection <br /> and metering CT's/VT's,protective relaying and generator control system. <br /> 5) Detailed information on the proposed equipment,including wiring diagrams,models and <br /> types. <br /> 6) Proposed relay settings for all interconnection required relays. <br /> 7) Detailed site plan of the Generation System. <br /> 8) Drawing(s)showing the monitoring system(as required per table 5A and section 5 of the <br /> "State of Minnesota Distributed Generation Interconnection Requirements". Including a <br /> drawing which shows the interface terminal block with the Area EPS monitoring system. <br /> 9) Proposed testing schedule and initial procedure,including; <br /> a) Time of day(after-hours testing required?). <br /> b) Days required. <br /> c) Testing steps proposed. <br /> Step 7 Final Design Review (By Area EPS) <br /> Within 15 business days of receipt of the information required in Step 6, The Area EPS <br /> Generation Interconnection Coordinator will provide the Applicant with an estimated time table for <br /> final review. If the information required in Step 6 is not complete, the Applicant will be notified, <br /> within 10 business days of what information is missing. No further review may be completed until <br /> the missing information is submitted. The 15-business day clock will restart with the new <br /> submittal. This final design review shall not take longer than 15 additional business days to <br /> complete, for a total of 30 business days. <br /> Interconnection Process for Distributed Generatip7 Systems <br />