BID TABULATIONCITY OF ELK RIVER2017 Street ImprovementsER303 bid tabBID TABULATIONBT - 7 OF 14ITEM NO.ITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION54 ADJUST FRAME AND RING CASTING 7 EACH $740.22 $5,181.54 $570.00 $3,990.00 $811.79 $5,682.53 $347.00 $2,429.0055 SEAL CATCH BASIN 31 EACH $155.15 $4,809.65 $300.00 $9,300.00 $261.00 $8,091.00 $267.00 $8,277.0056 RANDOM RIPRAP CLASS III 24.6 CU YD $121.53 $2,989.64 $100.00 $2,460.00 $82.10 $2,019.66 $64.10 $1,576.8657 GEOTEXTILE FILTER TYPE IV 86 SQ YD $5.52 $474.72 $2.00 $172.00 $5.15 $442.90 $2.40 $206.4058 4" CONCRETE WALK 25 SQ FT $6.37 $159.25 $6.85 $171.25 $8.40 $210.00 $8.50 $212.5059 6" CONCRETE WALK 990 SQ FT $7.44 $7,365.60 $8.00 $7,920.00 $7.60 $7,524.00 $7.95 $7,870.5060 CONCRETE CURB AND GUTTER DESIGN B412 18,806 LIN FT$11.72$220,406.32$12.60$236,955.60$12.90$242,597.40$11.70$220,030.2061 CONCRETE CURB AND GUTTER DESIGN B618 2,559 LIN FT$12.79$32,729.61$13.75$35,186.25$13.90$35,570.10$12.80$32,755.2062 6" CONCRETE DRIVEWAY PAVEMENT 1,397 SQ YD$52.97$73,999.09$57.00$79,629.00$55.00$76,835.00$57.70$80,606.9063 7" CONCRETE DRIVEWAY PAVEMENT 106 SQ YD$77.04 $8,166.24 $83.00 $8,798.00 $77.90 $8,257.40 $81.80 $8,670.8064 8" CONCRETE DRIVEWAY PAVEMENT 73 SQ YD$57.78 $4,217.94 $62.00 $4,526.00 $59.60 $4,350.80 $62.50 $4,562.5065 CONCRETE DRAINAGE FLUME 61 SQ YD $115.56 $7,049.16 $125.00 $7,625.00 $110.00 $6,710.00 $115.00 $7,015.0066 TRUNCATED DOMES 170 SQ FT $48.15 $8,185.50 $52.00 $8,840.00 $45.70 $7,769.00 $48.10 $8,177.0067 BITUMINOUS CURB 1,710 LIN FT $2.14 $3,659.40 $1.75 $2,992.50 $7.60 $12,996.00 $4.25 $7,267.5068 MAILBOX SUPPORT 15 EACH $101.65 $1,524.75 $110.00 $1,650.00 $223.00 $3,345.00 $102.00 $1,530.0069 INSTALL MAILBOX SUPPORT 104 EACH $42.80 $4,451.20 $45.00 $4,680.00 $152.00 $15,808.00 $42.80 $4,451.2070 TRAFFIC CONTROL 0.44 LUMP SUM $79,859.18 $35,138.04 $85,000.00 $37,400.00 $86,000.00 $37,840.00 $88,700.00 $39,028.0071 INSTALL SIGN SUPPORT 17 EACH$80.25$1,364.25$85.00$1,445.00$128.00$2,176.00$134.00$2,278.0072 ADJUST HANDHOLE 2 EACH$428.00$856.00$570.00$1,140.00$762.00$1,524.00$802.00$1,604.0073 RIGID PVC LOOP DETECTOR 6'x6' 4 EACH $909.51 $3,638.04 $1,700.00 $6,800.00 $1,220.00 $4,880.00 $1,280.00 $5,120.0074 SILT FENCE, TYPE MS 2,280 LIN FT $1.87 $4,263.60 $2.25 $5,130.00 $2.05 $4,674.00 $2.15 $4,902.0075 STORM DRAIN INLET PROTECTION 44 EACH $90.95 $4,001.80 $265.00 $11,660.00 $122.79 $5,402.76 $96.20 $4,232.8076 SEDIMENT CONTROL LOG TYPE COMPOST 3,450 LIN FT $1.87 $6,451.50 $2.70 $9,315.00 $3.10 $10,695.00 $3.20 $11,040.0077 STABILIZED CONSTRUCTION EXIT 0.44 LUMP SUM $5,200.25 $2,288.11 $2,500.00 $1,100.00 $3,900.00 $1,716.00 $21,400.00 $9,416.0078 CULVERT END CONTROLS 2 EACH $240.76 $481.52 $265.00 $530.00 $152.00 $304.00 $641.00 $1,282.0079 FERTILIZER TYPE 1 2,173 POUND $1.02 $2,216.46 $1.55 $3,368.15 $1.05 $2,281.65 $1.05 $2,281.6580 COMMON TOPSOIL BORROW (LV) 1,092 CU YD $35.85 $39,148.20 $25.90 $28,282.80 $30.27 $33,054.84 $23.50 $25,662.0081 SEEDING7.05 ACRE $374.50 $2,640.23 $9,800.00 $69,090.00 $4,120.00 $29,046.00 $4,280.00 $30,174.0082 SEED MIXTURE 25-131 1,549 POUND $3.20 $4,956.80 $4.50 $6,970.50 $2.85 $4,414.65 $2.95 $4,569.5583 EROSION CONTROL BLANKETS CATEGORY 3 3,125 SQ YD $1.55 $4,843.75 $2.10 $6,562.50 $1.00 $3,125.00 $1.05 $3,281.2584 HYDRAULIC NATURAL TACKIFIER 30,922 SQ YD $0.75 $23,191.50 $1.55 $47,929.10 $0.26 $8,039.72 $0.27 $8,348.9485 EROSION CONTROL 0.44 LUMP SUM $3,210.02 $1,412.41 $1,140.00 $501.60 $5,080.00 $2,235.20 $4,810.00 $2,116.4086 PAVEMENT MESSAGE EPOXY 45 SQ FT $5.73 $257.85 $6.00 $270.00 $5.10 $229.50 $5.35 $240.7587 4" SOLID LINE EPOXY 2,959 LIN FT $0.31 $917.29 $0.30 $887.70 $0.27 $798.93 $0.29 $858.1188 24" SOLID LINE EPOXY 43 LIN FT $6.88 $295.84 $7.00 $301.00 $6.10 $262.30 $6.40 $275.2089 4" BROKEN LINE EPOXY 622 LIN FT $0.31 $192.82 $0.30 $186.60 $0.27 $167.94 $0.29 $180.3890 4" DOUBLE SOLID LINE EPOXY 1,180 LIN FT $0.62 $731.60 $0.60 $708.00 $0.55 $649.00 $0.58 $684.4091 CROSSWALK EPOXY 270 SQ FT $3.67 $990.90 $3.70 $999.00 $3.25 $877.50 $3.40 $918.00Total Bid Schedule F$1,824,961.43$1,981,027.79$2,081,394.45$1,991,426.34SUMMARY OF BIDDING:$3,777,635.22 $4,160,829.85 $4,184,293.55 $4,281,551.13Error in calculation.Total Bid Schedule A through FNorth Valley, Inc. Veit & Company, Inc. Park Construction Company Hardrives, Inc.BID SCHEDULE "F" - LOCAL FUNDING - CONTINUEDESTIMATED QUANTITYNorth Valley, Inc. Veit & Company, Inc. Park Construction Company Hardrives, Inc.
|