Active Elk River <br />Monthly Progress Report – September 2019 <br />Multipurpose Facility <br />September 2-6 <br />▪Excavation and fill removal from the site continued as earthwork crews progressed in getting the <br />site up to proper grade. (1) <br />▪Utility crews continued to excavate and install the new water line and storm sewer piping. (2) <br />▪Mason crews completed blockwork for the Zamboni room and enclosed the area. <br />September 9-13 <br />▪The new water line installation completed. <br />▪Rebar layouts for the multipurpose facility’s foundation was laid. (5) <br />▪The south end of the site was graded which will become the material staging zone and designated <br />contractor parking area. <br />September 16-20 <br />▪ Foundation work continued and pouring of the footings began. (4) <br />September 23-27 <br />▪Foundation work is nearing completion! <br />▪Masons began blockwork in the northwest corner which will be the site of new locker rooms. (3) <br />▪Masonry work continues for the next few weeks to complete blockwork by late October. <br />(1) <br />(3) <br />(2) <br />(4)(5) <br />Item: 9