In order to meet the June 1 submittal date, staff recommend the following <br />review process: <br /> <br />Process Date <br />1) NCDA preliminary review and conceptual May 3, 2001 <br />approval of Preliminary Engineering <br />2) Executive Committee/CRCCC review of complete May 17, 24 <br />Preliminary Engineering Package <br />3) Mn/DOT Submittal to FTA June 1, 2001 <br />4) Release to Cities for review and comment (45 dayJune 1, 2001 <br />review period) <br />5) CRCCC Review of Cities' Comments and Final Mid-July, 2001 <br />Recommendation to Mn/DOT Commissioner <br /> <br />Action Requested: That the NCDA approve, in concept, the Preliminary <br /> Engineering of the Northstar Commuter Rail Project <br /> and authorize its distribution to the cities for review <br /> · and comment in accordance with the above schedule. <br /> <br /> <br />