CaPX 2020 <br />INTERIM REPORT <br />DECEMBER 2004 <br />ATTACHMENT F <br />PRELIMINARY RESULTS <br />The CapX 2020 technical team assumed that the generation modeled in the 2009 summer <br />model would exist in 2020 and would serve the load modeled in 2009. To address <br />anticipated load growth of 6,300 megawatts, the team solicited information from independent <br />power producers (including wind developers), resource planning entities within various <br />organizations, and the Midwest Independent Transmission System Operator's (MISO's) <br />generation interconnection queue. The team mapped the locations of these resources and <br />identified five generation regions: northern Minnesota, North Dakota and South Dakota, <br />southern Minnesota/northern Iowa, Wisconsin and the Twin Cities metropolitan area. These <br />are shown in Diagram 4. <br />Diagram 4 <br />23 <br />