Aug 15, 2002 <br /> <br />Northstar Corridor Rail Project <br /> <br />Timeline and Work Plan for the Remainder of 2002 <br /> <br />Overall Project Timeline <br />March 2002 Final ElS published <br />Fall 2002 Environmental Record of Decision <br />To be determined State Funding commitment (SF in the following items) <br />2-4 months after SF Begin final design <br />20 months after SF Full Funding Grant Agreement executed and approved <br />22 months after SF Construction begins <br />42 months after SF Service opens <br /> <br />If the 2003 legislature approves funding for Northstar, service will open in Dec 2006. <br /> <br />2002 Work Plan <br /> <br />Now until complete <br /> <br />Now-Nov <br />Now-Jan <br />Nov-Jan <br />Now until funding <br />Now until funding <br /> <br />Now until second grant <br />approved <br /> <br />Continue providing FTA with material to finish the <br />Record of Decision <br />Update project information with current data <br />Prepare RFP for Minneapolis multimodal hub study <br />Brief legislative staff <br />Continue developing Standard Operating Procedures <br />Continue preparation of final design Request for <br />Proposals <br />Prepare RFP for Twin Cities rail network capacity <br />analysis <br /> <br /> <br />