<br />ARTICLE 1 GENERAL PROVISIONS <br />!i 1.1 RELATIONSHIP OF PARTIES <br />The Construction Manager accepts the relationship of trust and confidence established with the Owner by this <br />Agreement, and covenants with the Owner to furnish the Construction Manager's reasonable skill and judgment and <br />to cooperate with the Architect in furthering the interests of the Owner. The Construction Manager shall furnish <br />construction administration and management services and use the Construction Manager's best efforts to perform the <br />Project in an expeditious and economical manner consistent with the interests ofthe Owner. The Owner shall <br />endeavor to promote harmony and cooperation among the Owner, Architect~ Construction Manager and other <br />persons or entities employed by the Owner for the Project. <br /> <br />!i 1.2 GENERAL CONDITIONS <br />For the Construction Phase, the General Conditions of the contract shall be the AIA@ Document A20 1"'-1997, <br />General Conditions of the Contract for Construction, which is incorporated herein by reference. For the <br />Preconstruction Phase, or in the event that the Preconstruction and Construction Phases proceed concurrently, <br />A20jTM-1997 shall apply to the Preconstruction Phase only as specifically provided in this Agreement. The term <br />tlContractortl as used in A201TM....-1997 shall mean the Construction Manager. <br /> <br />ARTICLE 2 CONSTRUCTION MANAGER'S RESPONSIBILITIES <br />The Construction Manager shall perform the services described in this Article. The services to be provided under <br />Sections 2.1 and 2.2 constitute the Preconstruction Phase sernces. If the Owner and Construction Manager agree, <br />after consultation with the Architect, the Construction Phase may commence before the Preconstruction Phase is <br />completed, in which case both phases will proceed concurrently. <br /> <br />!i 2.1 PRECONSTRUCTlON PHASE <br />!i 2.1.1 PRELIMINARY EVALUATION <br />The Construction Manager shall provide a preliminary evaluation of the Owner's program and Project budget <br />requirements, each in terms of the other. <br /> <br />!i 2.1.2 CONSULTATION <br />The Construction Manager with the Architect shall jointly schedule and attend regular meetings with the Owner. <br />The Construction Manager shall consult with the Owner and Architect regarding site use and improvements and the <br />selection of materials, building systems and equipment. The Construction Manager shall provide recommendations <br />on construction feasibility; actions designed to minimize adverse effects of labor or material shortages; time <br />requirements for procurement, installation and construction completion; and factors related to construction cost, <br />including estimates of alternative designs or materials, preliminary budgets and possible economies. <br /> <br />!i 2.1.3 PRELIMINARY PROJECT SCHEDULE <br />When Proj ect requirements described in Section 3.1.1 have been sufficiently identified, the Construction Manager <br />shall prepare, and periodically update, a preliminary Project schedule for the Architect's review and the Owner's <br />approval. The Construction Manager shall obtain the Architect's approval of the portion of the preliminary Project <br />schedule relating to the performance of the Architect's services. The Construction Manager shall coordinate and <br />integrate the preliminary Project schedule with the services and activities of the Owner, Architect and Construction <br />Manager. As design proceeds, the preliminary Project schedule shall be updated to indicate proposed activity <br />sequences and durations, milestone dates for receipt and approval of pertinent information, submittal of a <br />Guaranteed Maximum Price proposal, preparation and processing of shop drawings and samples, delivery of <br />materials or equipment requiring long-lead-time procurement, Owner's occupancy requirements showing portions of <br />the Project having occupancy priority, and proposed date of Substantial Completion. If preliminary Project schedule <br />updates indicate that previously approved schedules may not be met, the Construction Manager shall make <br />appropriate recommendations to the Owner and Architect. <br /> <br />!i 2.1.4 PHASED CONSTRUCTION <br />The Construction Manager shall make recommendations to the Owner and Architect regarding the phased issuance <br />of Drawings and Specifications to facilitate phased construction of the Work, if such phased construction is <br />appropriate for the Project, taking into consideration such factors as economies, time of performance, availability of <br />labor and materials, and provisions for temporary facilities. <br /> <br />!i 2.1.5 PRELIMINARY COST ESTIMATES <br />!i 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other <br />basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval oftbe <br />Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques. <br />