Laserfiche WebLink
Mr. Justing Femrite, P.E. <br />December 3, 2024 <br />Page: 3 <br />Project Schedule <br />We understand the importance of meeting desired timelines to enable construction to occur in 2025 <br />The below schedule assumes easements will not delay gravity design construction or that lift station <br />controls and generators don't cause delays to the forcemain option. <br />Item Date <br />Notice to Proceed from City <br />December 16, 2024 <br />Plans and Specifications Complete <br />February 28, 2025 <br />Bid Opening <br />March 31, 2025 <br />Award Bid <br />April 7, 2025 <br />Construction Start <br />May 2025 <br />Substantial Completion <br />November 21, 2025 <br />Final Completion <br />December 26, 2025 <br />Project Fees <br />Bolton & Menk will perform the work as described in the Work Plan. Our proposed fees for services are <br />hourly, not to exceed, as follows: <br />Business Center Drive Extension <br />Topo Surveying, Drone Imagery, Temp Easements <br />Design through Bidding Fee <br />$ 16,313.00 <br />$ 48,510.00 <br />Construction Services Fee $ 57,608.00 <br />Total Base Fee $ 122,431.00 <br />Summary <br />Bolton & Menk has field crews available to begin surveying and we also have engineers and technicians <br />available to begin evaluating the lift station/forcemain alternative. <br />If there are any questions, please contact me at the number listed below. <br />Sincerely, <br />Bolton & Menk, Inc. <br />J--L� -W <br />Jason W. Cook, P.E. <br />Principal Engineer <br />(763) 200-2444 <br />H:\ELKR\$_City of Elk River MN\Meadowwoods Village Sewer Extension Proposal.docx <br />Bolton & Menk is an equal opportunity employer. <br />