cost of program requirements using area, volume, or similar conceptual estimating techniques. If the Architect or
<br />Construction Manager suggests alternative materials and systems, the Construction Manager shall provide cost
<br />evaluations of those alternative materials and systems.
<br />§ 3.1.6.2 As the Architect progresses with the preparation of the Schematic Design, Design Development and
<br />Construction Documents, the Construction Manager shall prepare and update, at appropriate intervals agreed to by the
<br />Owner, Construction Manager and Architect, an estimate of the Cost of the Work with increasing detail and refinement.
<br />The Construction Manager shall include in the estimate those costs to allow for the further development of the design,
<br />price escalation, and market conditions, until such time as the Owner and Construction Manager agree on a
<br />Guaranteed Maximum Price for the Work. The estimate shall be provided for the Architect's review and the Owner's
<br />approval. The Construction Manager shall inform the Owner and Architect in the event that the estimate of the Cost of
<br />the Work exceeds the latest approved Project budget, and make recommendations for corrective action.
<br />§ 3.1.6.3 If the Architect is providing cost estimating services as a Supplemental Service, and a,discrepancy exists
<br />between the Construction Manager's cost estimates and the Architect's cost estimates, the Construction Manager and
<br />the Architect shall work together to reconcile the cost estimates.
<br />§ 3.1.7 As the Architect progresses with the preparation of the Schematic Design, Design Development and
<br />Construction Documents, the Construction Manager shall consult with the Owner and Architect and make
<br />recommendations regarding constructability and schedules, for the Architect's review and the Owner's approval.
<br />§ 3.1.8 The Construction Manager shall provide recommendations and information to the Owner and Architect
<br />regarding equipment, materials, services, and temporary Project facilities.
<br />§ 3.1.9 The Construction Manager shall provide a staffing plan for Preconstruction Phase services for the Owner's
<br />review and approval.
<br />§ 3.1.10 If the Owner identified a Sustainable Objective in Article 1, the Construction Manager shall fulfill its
<br />Preconstruction Phase responsibilities as required in AIA Document E234Tm--2019, Sustainable Projects Exhibit,
<br />Construction Manager as Constructor Edition, attached to this Agreement.
<br />§ 3.1.11 Subcontractors and Suppliers
<br />§ 3.1.11.1 If the Owner has provided requirements for subcontractor procurement in section 1.1.14, the Constru(
<br />Manager shall provide a subcontracting plan, addressing the Owner's requirements, for the Owner's review and
<br />approval.
<br />§ 3.1.11.2 The Construction Manager shall develop bidders' interest in the Project.
<br />§ 3.1.11.3 The processes described in Article 9 shall apply if bid packages will be issued
<br />Phase.
<br />§ 3.1.12 Procurement
<br />All Work that is subject to the Uniform Municipal Contracting Law, Minnesota Statutes, Section 471.34,5 ("UMCL")
<br />shall be publicly bid in accordance with Minnesota law and Construction Manager shall do all things necessary to
<br />effectuate Owner's compliance with public bidding, where applicable, in Owner's sole discretion. The Construction
<br />Manager shall prepare, for the Architect's review and the Owner's acceptance, a procurement schedule for items that
<br />must be ordered in advance of construction. The Construction Manager shall expedite and coordinate the ordering and
<br />delivery of materials that must be ordered in advance of construction. If the Owner agrees to procure any items prior to
<br />the establishment of the Guaranteed Maximum Price, the Owner shall procure the items on terms and conditions
<br />acceptable to the Construction Manager, provided Owner is satisfied that such procurement complies with law. Upon
<br />the establishment of the Guaranteed Maximum Price, the Owner shall assign all contracts for these items to the
<br />Construction Manager and the Construction Manager shall thereafter accept responsibility for them.
<br />§ 3.1.13 Compliance with Laws
<br />The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, rules and regulations, and
<br />lawful orders of public authorities applicable to its performance under this Contract, and with equal employment
<br />opportunity programs, and other programs as may be required by governmental and quasi -governmental authorities.
<br />AIA Do—ent A133' - 2019. Copyright © 1991, 2003, 2009, and 2019 by The American Institute of Architects. All rights reserved. The
<br />"Ac—,can Institute of 1ich to ts," "AIA ,' the AIA Logo , <; and `AIA Contract Doument are registered tt edema ks and mn ay ot b used
<br />without permission. This draft was produced by AIA software at 13:58:42 ET on 06/29/2020 under Order No.2067434383 which expires on
<br />04/02/2021, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms