SCHEDULE 3 - DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br />17.1.The Interconnection Customer shall be available to meet on site with the Area EPS <br />Operator within five (5) Business Days of signing the Facilities Study Agreement. The <br />personnel furnished by the Interconnection Customer for this site visit shall bring <br />detailed information on the site layout. The Area EPS Operator may request the <br />Interconnection Customer physically places stakes at the locations of major <br />components. <br /> <br />17.2.The Interconnection Customer shall furnish a final site plan detailing the location of <br />major equipment at the time this agreement is returned. The Point of Common <br />Coupling (PCC) and Point of Distributed Resource Connection (PoC) shall be clearly <br />marked. The site plan shall depict any nearby roads and be labeled with the road <br />name. Accurate dimensions shall be included on the site plan. The proper emergency <br />(911) address, corresponding to the site, shall be labeled on the site plan. <br /> <br />17.3.The Interconnection Customer shall furnish a final one-line diagram detailing the <br />electrical connections between major components. The one-line shall be returned <br />with the signed Facilities Study Agreement. <br /> <br />17.4.Technical cut sheets on all equipment related to metering shall be provided by the <br />Interconnection Customer along with the signed Facilities Study Agreement. <br /> <br />17.5.If available, copies of the Conditional Use Permits(s) from all necessary authorities <br />shall be returned by the Interconnection Customer with the signed Facilities Study <br />Agreement. <br /> <br />17.6.The Interconnection Customer shall secure any necessary easements from private <br />land owners prior to signing the Facilities Study Agreement. Documentation of any <br />such agreements shall be provided to the Area EPS Operator. <br /> <br />M-MIP Facility Study Agreement _January 2019 6 <br /> <br />267 <br />