SCHEDULE 3 - DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br />The Party will suffer significant uncompensated economic or operational harm from <br />the delay, or <br /> <br />Attainment of the same milestone has previously been delayed, or <br /> <br />The Party has reason to believe the delay in meeting the milestone is intentional or <br />unwarranted notwithstanding the circumstance explained by the Party proposing <br />the amendment. <br /> <br />If the Party affected by the failure to meet a milestone disputes the proposed extension, <br />the affected Party may pursue dispute resolution as described in the Overview Process <br />document. <br /> <br />11.2.Metering <br />Any metering requirements necessitated by the use of the DER system shall be installed <br />-related costs will be included <br />in the final invoice of interconnection costs to the Interconnection Customer. The <br />Interconnection Customer is also responsible for metering replacement costs not <br /> The Area EPS <br />Operator may charge Interconnection Customers an ongoing metering-related charge <br />for an estimate of ongoing metering-related costs specifically demonstrated. <br /> <br />11.3.Inspection, Testing and Commissioning <br />Upon completing construction of the DER system, the Interconnection Customer will <br />cause the DER system to be inspected or otherwise certified by the appropriate local <br />electrical wiring inspector with jurisdiction. The Interconnection Customer shall then <br />Interconnection Facilities prior to interconnection pursuant to Minnesota Technical <br />Requirements. Commissioning tests of the Interconnection Cus <br />equipment shall be performed pursuant to applicable codes and standards of <br /> <br /> <br />The Interconnection Customer shall notify the Area EPS Operator of testing and <br />inspection no fewer than five (5) Business Days in advance, or as may be agreed to by <br />the Parties. The Interconnection Customer shall provide to the Area EPS Operator a <br />testing procedure that will be followed on the day of testing and inspection no fewer <br />than ten (10) Business Days prior to the testing and inspection date. The testing <br />procedure should include tests and/or inspections to confirm the DER system will meet <br />the technical requirements of interconnection. The Area EPS Operator shall review the <br />testing procedure for completeness and notify the Interconnection Customer if the <br />13 <br /> <br />224 <br />