Laserfiche WebLink
SCHEDULE 3 - DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br />2Application Submission <br />2.1.Fast Track Process Application <br />The Interconnection Customer shall complete the Standard Interconnection Application <br />and submit it to the Area EPS Operator to initialize the Interconnection Process. A <br />completed Interconnection Application will include the following: <br /> <br />A completed Interconnection Application signed by the Interconnection <br />Customer. <br /> <br />A non-refundable processing fee indicated in Section 2.3. <br /> <br />A site layout drawing of the proposed DER system. <br /> <br />A one-line diagram of the proposed DER system showing the point of common <br />Distribution System. <br /> <br />All equipment manufacturer specification sheets. <br /> <br />Documentation of site control indicated in Section 2.5. <br /> <br />2.2.Professional Licensed Engineer Signature <br />The one-line diagram submitted with the Interconnection Application will require a <br />signature from a professional engineer licensed in the State of Minnesota certifying the <br />DER was designed in conformance to the Minnesota Technical Requirements for the <br />following conditions: <br /> <br />4 <br />Certified equipment is greater than 250 kW. <br /> <br />Non-certified equipment is greater than 20 kW. <br /> <br />2.3.Processing Fee <br />The processing fee will differ for a Fast Track Interconnection Application depending on <br />the type of equipment utilized as seen in Table 2.1. <br /> <br /> <br />4 <br />Additional information regarding certified equipment is found in Section 14 and Section 15 of the Process <br />Overview document. <br />2 <br /> <br />191 <br />