Laserfiche WebLink
Page 2 of 3 <br /> Project Purpose <br /> The highway needs reconstruction to address grading, pavement, curb and gutter, ADA and storm <br /> sewer issues. <br /> Project Description <br /> TH 10 reconstruction from Xenia Ave to 4th Street in Elk River and trail construction from Simonet <br /> Drive to Lowell Ave. <br /> Other activities include: <br /> Close Oxford Ave and Norfolk Ave to TH 10. <br /> Remove left turn lane to Norfolk Ave. <br /> Add second left turn lane and extend turn lanes at Proctor Ave for east bound traffic. <br /> Upgrade ADA (Peds & crossings) at Proctor Ave and Upland Ave. <br /> Replace signals at Proctor Ave. and Upland Ave. <br /> Construct right turn lane on Proctor Ave for north bound traffic (requested by city). <br /> Extend street lighting from Proctor Ave to Upland Ave (requested by city). <br /> Planned Project Schedule <br /> The project is schedule for a 12/18/2020 letting with construction beginning spring/summer 2021. <br /> The construction is planned to be completed in 2021. During construction, TH 10 will be reduced <br /> to one lane of traffic for east bound while maintaining two lanes of traffic for west bound. <br /> City's Estimated Project Costs <br /> Some project costs are the City's responsibility, as detailed in MnDOT's cost participation policy. <br /> (See the policy and the Cost Participation and Maintenance with Local Units of Government <br /> Manual at MnDOT's this website: http://www.dot.state.mn.us/policy/financial/fmO11.html). <br /> Attached is MnDOT's current estimate of the City's costs for S.P. 7102-135. <br /> The estimate includes costs for signal replacements at Proctor Avenue and Upland Avenue, right <br /> turn lane construction for north bound traffic on Proctor Avenue and street lighting replacement and <br /> new installations. <br /> As shown on the attached, the City of Elk River's total cost participation for SP 7102-135 is <br /> currently estimated to be $200,000-$250,000. <br /> This estimate does not include engineering, city utility work or trail lighting costs. <br /> The total project cost is estimated to be $8,900,000. <br /> This project will involve a turn-back of 4th Street NW from Morton Ave to TH 10 once all <br /> construction is completed. Image attached. <br /> An Equal Opportunity Employer <br /> O 0 00" <br />