W <br /> WASTE MANAGEMENT <br /> 9.9.4 Immediately prior to such partial occupancy or use, the Owner's Authorized Representative and <br /> Contractor shall jointly inspect the area to be occupied or the portion of the Work to be used in <br /> order to determine and record the condition of the Work. <br /> 9.9.5 Partial occupancy or use of a portion or portions of the Work shall not constitute acceptance of <br /> Work not complying with requirements of the Contract Documents. <br /> 9.10 Final Completion and Final Payment <br /> 9.10.1 When Contractor believes Final Completion of the Work has been achieved, Contractor shall <br /> review all Contract Documents and inspect the Work. Prior to Contractor notification to Owner's <br /> Authorized Representative that Work is complete and ready for final inspection, Contractor shall <br /> submit an affidavit that the Work has been inspected and the Work is complete in accordance <br /> with requirements of Contract Documents. <br /> 9.10.2 Within fifteen (15) Days after receipt of Contractor's written notice that Work is ready for final <br /> inspection and acceptance, and on receipt of final Application for Payment, Owner's Authorized <br /> Representative will make such inspection. When Owner's Authorized Representative finds the <br /> Work acceptable under the Contract Documents and Final Completion has been achieved, the <br /> Owner's Authorized Representative will issue a certificate of Final Completion stating that to the <br /> best of Owner's Authorized Representative's knowledge, information, and belief, the Work has <br /> been completed in accordance with terms and conditions of the Contract Documents, and will <br /> issue a final Recommendation for Payment. <br /> 9.10.3 Should Work be found not in compliance with requirements of Contract Documents, Owner's <br /> Authorized Representative shall notify Contractor in writing of items of non-compliance. Upon <br /> correction of such non-complying items, Owner's Authorized Representative shall issue a <br /> Certificate of Final Completion to Contractor as provided in Article 9.10.2. <br /> 9.10.4 Final payment shall not be become due to the Contractor until each of the following have been <br /> submitted to Owner by Contractor, each of which shall be a condition precedent to final payment. <br /> .1 an affidavit that payrolls, invoices for materials and equipment, and other indebtedness of <br /> the Contractor connected with the Work(less amounts withheld by Owner)have been paid <br /> or otherwise satisfied; <br /> .2 if required by Owner's Authorized Representative, Contractor waivers or releases of Liens <br /> or Claims from Subcontractors and laborers; <br /> .3 a certificate evidencing that insurance required by the Contract Documents to remain in <br /> force after final payment is currently in effect and will not be canceled, or materially <br /> changed, until at least thirty(30) Days written notice has been given to Owner; <br /> .4 a written statement that Contractor knows of no substantial reason that the insurance will <br /> not be renewable to cover the correction and warranty period required by the Contract <br /> Documents; <br /> .5 consent of Surety to final payment; <br /> .6 any required maintenance or other Bonds; and <br /> .7 Record Drawings and any maintenance manuals, results of tests, inspections, and <br /> approvals required by the Contract Documents. <br /> 9.10.5 If, after Substantial Completion of the Work, Final Completion thereof is materially delayed <br /> through no fault of Contractor, or by issuance of Change Orders affecting Final Completion, and <br /> the Owner's Authorized Representative so confirms, Owner may, upon application by Contractor <br /> and recommendation by the Owner's Authorized Representative, and without terminating the <br /> Agreement, make payment of the balance due for that portion of the Work that is fully completed <br /> and accepted. <br /> 9.10.6 Owner shall make final payment to Contractor within sixty(60)Days after the Owner's Authorized <br /> Representative issues the final certificate of Completion and the final Recommendation for <br /> Payment, subject to limitations, if any, as stated in the Supplementary Conditions and provided <br /> that Contractor has satisfied all of the conditions precedent listed in Article 9.10.4. <br /> 32 Jun-17 <br /> Ver.2.0 <br />