Laserfiche WebLink
W <br /> WASTE MANAGEMENT <br /> .4 whenever the cost for an allowance item is more than, or less than, the allowance, the <br /> Contract Price shall be adjusted accordingly by Change Order. The amount of the Change <br /> Order shall be the difference between actual costs and the amount of the allowance stated <br /> in the Contract Documents, and shall be offset against credits due to Owner in the amount <br /> of the allowance. Any Change Order which would result in an increase in the Contract <br /> Price shall be subject to the approval of the Owner's Authorized Representative, which <br /> approval shall not unreasonably be withheld. <br /> 9.4 Applications For Payment <br /> 9.4.1 Each month, not later than the tenth (10th) Day of the month, the Contractor shall submit to the <br /> Owner's Authorized Representative, an itemized Application for Payment for Work completed <br /> during the previous month. <br /> 9.4.2 The Application for Payment shall be supported by such data and documentation substantiating <br /> Contractor's right to payment (including evidence of payment of Subcontractors and Suppliers) <br /> as the Owner's Authorized Representative may require. Such documentation may include: <br /> .1 For any Project where Contractor does not provide a payment Bond, conditional Lien <br /> releases from all Subcontractors who are to be paid from the current pay application; and <br /> .2 Unconditional Lien releases from all Subcontractors up to and through the last pay <br /> application that Owner has paid. <br /> 9.4.3 Subject to provisions of the Contract Documents, the amount of each Application for Payment <br /> shall be compiled as follows: <br /> .1 The Contract Price of the Work completed from commencement of the Work through the <br /> end of the previous month, as determined by multiplying the number of units completed of <br /> each item of the Work by the Unit Price of that item, or by multiplying the percentage of <br /> completion of each portion of the Work by the Lump Sum Price allocated to that portion of <br /> the Work listed in the Schedule of Values, as applicable; <br /> .2 Plus that portion of the Contract Price, properly substantiated by certified copies of invoices <br /> and freight bills, for non-perishable materials and equipment not yet incorporated in the <br /> Work but delivered and suitably stored at the Site or at another location agreed to by the <br /> Owner's Authorized Representative in writing, for subsequent incorporation into the <br /> completed construction, less 15 percent; <br /> .3 Less retainage on the completed portion of the Work of 10%for progress payments through <br /> Substantial Completion of the Work; <br /> .4 Less any discounts Owner is entitled to take based on past, prompt payments as set forth <br /> in Article 9.7.2; <br /> .5 Less any amounts Owner is entitled to withhold under Article 9.6, any other article <br /> authorizing withholding of payments or any Applicable Laws; and <br /> .6 Less the total of previous payments made by Owner. <br /> 9.5 Recommendations or Payment <br /> 9.5.1 The Owner's Authorized Representative will, within ten (10) Days after receipt of Contractor's <br /> Application for Payment: <br /> .1 Issue a Recommendation for Payment for the full amount of the Application; or <br /> .2 Issue a Recommendation for Payment for a portion of the amount of the Application. In the <br /> event Owner's Recommendation for Payment is less than the full amount of the Application, <br /> Owner will notify Contractor of the reasons therefore in writing and request the Contractor <br /> to make corrections or provide additional information to substantiate the remaining portion. <br /> Contractor shall make the corrections and provide the additional information, and resubmit <br /> the Application for Payment for the remaining portion; or <br /> .3 Return the Application to the Contractor for corrections or additional information. Contractor <br /> shall make the corrections and provide the additional information and resubmit the <br /> Application for Payment; or <br /> .4 Decline to recommend payment on the basis of the provisions in Article 9.6. <br /> 29 Jun-17 <br /> Ver.2.0 <br />