Laserfiche WebLink
SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> An Interconnection Application will retain its queue number even when it is moved into <br /> a different process track. An Interconnection Application can lose its queue position if <br /> the Interconnection Customer misses timelines in the applicable process track. The <br /> Interconnection Customer and Area EPS Operator have the opportunity to request <br /> timeline extensions which are explained in detail in Section 10. <br /> 4.8. Site Control <br /> Documentation of site control must be submitted with the Interconnection Application. <br /> Site control may be demonstrated by any of the following: <br /> • Ownership of, a leasehold interest in, or a right to develop a site for the purpose of <br /> constructing the DER system. <br /> • An option to purchase or acquire a leasehold site for constructing the DER system. <br /> • An exclusivity or other business relationship between the Interconnection <br /> Customer and the entity having the right to sell, lease, or grant to the <br /> Interconnection Customer the right to possess or occupy a site for constructing the <br /> DER system. <br /> For DER in the Simplified Process, proof of site control may be demonstrated by the site <br /> owner's signature on the Simplified Interconnection Application. <br /> 5 Pre-Application Report <br /> 5.1. Pre-Application Report Requests <br /> The Interconnection Customer may submit a Pre-Application Report Request, including <br /> a non-refundable fee of$300, for a Pre-Application Report on a proposed project at a <br /> specific site.The Interconnection Customer must fill out the Pre-Application Request <br /> form as completely as possible. The Area EPS Operator shall provide the readily <br /> available data listed in Section 5.3 within fifteen (15) Business Days of receipt of a <br /> completed request form and payment.The Pre-Application Report produced by the <br /> Area EPS Operator is non-binding, does not confer any rights, and does not preclude <br /> the Interconnection Customer from any interconnection process steps including <br /> submission of the Interconnection Application. <br /> 5.2. Information Provided <br /> Using the information provided in the Pre-Application Report Request form, the Area <br /> EPS Operator will identify the substation/area bus, bank or circuit likely to serve the <br /> proposed PCC. This selection by the Area EPS Operator does not necessarily indicate, <br /> after application of the screens and/or study, that this would be the circuit the project <br /> 9 <br /> 144 <br />