SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> 3.3. Simplified Process <br /> An application to interconnect a certified', inverter-based DER system no larger than 20 <br /> kilowatts (kW) shall be evaluated under the Simplified Process. A common form of DER <br /> inverter certification is UL 1741. Proposed DER systems that require Area EPS system <br /> modifications to accommodate the interconnection do not qualify for the Simplified <br /> Process. A transformer change, fusing upgrades or line extensions are common <br /> examples of Area EPS system modification. Simplified Process eligibility does not imply <br /> or indicate the Interconnection Application will pass the initial review screens. Failure <br /> to pass the screens will route the Interconnection Application to the Fast Track Process. <br /> 3.4. Fast Track Process <br /> An application to interconnect a DER shall be evaluated under the Fast Track Process if <br /> the eligibility requirements are not exceeded in Table 3.2 and the application does not <br /> qualify for the Simplified Process. Fast Track eligibility for DERs is determined based <br /> upon the generator type, the size of the generator, voltage of the line, and the location <br /> and type of line at the Point of Common Coupling, (PCC). All synchronous and induction <br /> machines must be no larger than 2 MW to be eligible for Fast Track Process <br /> consideration. <br /> Table 3.2. Fast Track Eligibility for DER <br /> 2 Fast Track Eligibility for certified, <br /> Fast Track Eligibility 3 <br /> inverter-based DER on a Mainline <br /> Line Voltage Regardless of <br /> and <_2.5 Electrical Circuit Miles from <br /> Location <br /> Substation4 <br /> < 5 kV <_500 kW <_ 500 kW <br /> >_ 5kV and < 15kV <_ 1MW <_ 2MW <br /> >_ 15kV and <30kV <_ 2MW <_4MW <br /> >_30kV and <_69kV <_4MW <_ 5MW <br /> In addition to the size threshold, the Interconnection Customer's proposed DER must <br /> meet the codes, standards and certification requirements found in Section 15 and <br /> Section 14. <br /> 'Additional information regarding certified equipment is found in Sections 14 and 15. <br /> 2 Synchronous and induction machine eligibility is limited to no more than 2 MW even when line voltage is greater <br /> than 15 kV. <br /> 3 For purposes of this table,a Mainline is the three-phase backbone of a circuit. It will typically constitute lines with <br /> wire sizes of 4/0 American wire gauge,266 kcmil, 336.4 kcmil, 397.5 kcmil,477 kcmil and 795 kcmil. <br /> 4 An Interconnection Customer can determine this information about its proposed interconnection location in <br /> advance by requesting a pre-application report described in Section 5. <br /> 5 <br /> 140 <br />