SCHEDULE 3—INTERCONNECTION PROCESS,TECHNICAL REQUIREMENTS,AND OPERATING PROCEDURES <br /> v) Synchronization of CustomerGeneration- <br /> (1)An automatic synchronizer with synch-check relaying is required for unattended automatic quick <br /> open transition,closed transition or soft loading transfer systems. <br /> (2)To prevent unnecessary voltage fluctuations on the Area EPS, it is required that the synchronizing <br /> equipment be capable of closing the Distributed Generation into the Area EPS within the limits <br /> defined in IEEE 1547. Actual settings shall be determined by the Registered Professional Engineer <br /> establishing the protective settings for the installation. <br /> (3)Unintended Islanding — Under certain conditions with extended parallel operation, it would be <br /> possible for a part of the Area EPS to be disconnected from the rest of the Area EPS and have the <br /> Generation System continue to operate and provide power to a portion of the isolated circuit. <br /> This condition is called "islanding". It is not possible to successfully reconnect the energized <br /> isolated circuit to the rest of the Area EPS since there are no synchronizing controls associated <br /> with all of the possible locations of disconnection. Therefore, it is a requirement that the <br /> Generation System be automatically disconnected from the Area EPS immediately by protective <br /> relays for any condition that would cause the Area EPS to be de-energized. The Generation <br /> System must either isolate with the customer's load or trip.The Generation System must also be <br /> blocked from closing back into the Area EPS until the Area EPS is reenergized and the Area EPS <br /> voltage is within Range B of ANSI C84.1 Table 1 for a minimum of 1 minute. Depending upon the <br /> size of the Generation System it may be necessary to install direct transfer trip equipment from <br /> the Area EPS source(s) to remotely trip the generation interconnection to prevent islanding for <br /> certain conditions <br /> vi)Disconnection—the Area EPS operator may refuse to connect or may disconnect a Generation System <br /> from the Area EPS under the following conditions: <br /> (1)Lack of approved Standard Application Form and Standard Interconnection Agreement. <br /> (2)Termination of interconnection by mutual agreement. <br /> (3) Non-Compliance with the technical or contractual requirements. <br /> (4)System Emergency or for imminent danger to the public or Area EPS personnel(Safety). <br /> (5)Routine maintenance, repairs and modifications to the Area EPS.The Area EPS operator shall <br /> coordinate planned outages with the Interconnection Customer to the extent possible. <br /> Interconnection Process for Distributed Generatic Systems <br />