User Agreement that defines the flow and pollutant limits that are allocated to Waste <br />Management. <br />6.3 Implementation Schedule <br />The proposed implementation schedule for modification of Waste Management's current <br />leachate management practices include piloting and testing with full scale operation, design, <br />permitting, and construction. Testing is proposed for a period of 6-9 months following <br />construction and start-up of the activated sludge treatment processes in fall 2015. Upon <br />successful pilot operation, Waste Management may proceed with final design and construction as <br />desired with an anticipated timeframe of completion in the fall of 2017. <br />City of Elk River, Minnesota —121.109643 Page 22 <br />Elk RiveriWaste Management Leachate Study Prepared by Bolton & Menk, Inc. <br />