Laserfiche WebLink
department for Met Council (651-602-4701). Met Council would classify this as a shod-term <br />discharge (lasting 2 to 3 weeks) from an out of area location. Several fees would be involved <br />and were roughly calculated for the City of Elk River. Actual liquid sludge strengths were not <br />available so they were assumed to be typical levels for preliminary estimates. · Permit application with $300 fee <br /> · Strength charge: Based on 25,000 mg/I of TSS (total suspended solids) and 20,000 <br /> mg/I of COD (carbonaceous oxygen demand), the cost for communities within the metro <br /> service area would be $36.00/1000 gallons. This charge would be approximately <br /> doubled since Elk River is outside of the Metro Area, which would make it $72.0011000 <br /> gallons. <br /> · The industrial load charge includes the strength charge plus a volume charge of <br /> $1.34/1000 gallons. <br /> · Out of Service Area charge of $50 per load. Loads are typically 5000 gallons. This <br /> equates to a cost of $1011000 gallons. <br /> <br />This totals approximately $84/1000 gallons, $0.084 per gallon or $45,000 based on the <br />estimated amount of sludge. This does not include trucking costs. The City does not have <br />equipment available to haul liquid waste. <br /> <br />Met Council would need the completed permit application and $300 fee submitted. The sludge <br />strength and heavy metal concentration would need to be submitted with the permit. A letter <br />describing the reason for discharging to Met Council would also be required. Once submitted, <br />they would determine which plant location would be available to accept the liquid sludge. They <br />would then write an approval form that would need to be authorized. They said the process can <br />take up to two weeks, and that accepting sludge within two or three weeks would be possible. <br /> <br />RECOMMENDATION <br />It is recommended that the City select the landfill option. The estimated cost of $35,000 is very <br />rough since several assumption were involved beginning with the amount of sludge that needs <br />to be removed from the storage tank. The digester project contractor has been contacted and <br />can begin temporary piping to the secondary digester July 19th. Plant staff is conducting the <br />necessary tests required by the landfill to allow disposal and should be approved by next week. <br /> <br />Once the sludge is approved by the landfill, the contractor that will remove the sludge and dry <br />will mobilize equipment to the plant site. The sludge drying rate was estimated at 3000 gallons <br />per hour. Based on an 8-hour day, this would take approximately 22 days. The City should <br />begin emptying the tank with the least amount of sludge. That tank could then be used to hold <br />the primary digester sludge while it is taken offline and the other tank can continue to be <br />emptied. City staff plans to have the primary digester offiine by early August. <br /> <br />Once the tank is empty, the digester project contractor will began removal of the existing cover. <br />The structural damage will be assessed at this time and a change order is possible. <br /> <br />Distribution: <br /> Gary Leirmoe, City of Elk River WWTP <br /> Lori Johnson, City of Elk River Finance Director <br /> Terry Maurer, HRG <br /> <br />C:\Documents and Settings\jmiller. ELKRIVERPD\Local Settings\Temporary lnternet Files\OLK20\mem-071304- 3 <br />coverproblemsl 1 .doc <br /> <br /> <br />