Table 5.3 <br /> Preliminary Cost Estimates for Heat Drying Biosolids Option <br /> Elk River Wastewater Treatment Facilit <br /> Item Cost <br /> Mobilization $300,000 <br /> Site Work $200,000 <br /> Site Piping $100,000 <br /> Building(12,000 sq ft) $1,560,000 <br /> Polymer Feed System $50,000 <br /> Pumps/Piping $150,000 <br /> Dewatering Equipment $600,000 <br /> Sludge Storage Aeration Equipment $150,000 <br /> Heat Drying Equipment $4,000,000 <br /> Conveying Systems $50,000 <br /> Odor Control System $150,000 <br /> Mechanical $750,000 <br /> Electrical/Controls $800,000 <br /> Total Construction Cost $8,860,000 <br /> Contingency(10%) $886,000 <br /> En ineerin /Admire(15%) $1,329,000 <br /> Total Project Cost $11,075,000 <br /> 5.3.3. Regionalization <br /> Table 5.4 presents the cost estimate for the Regionalization Biosolids Option. <br /> Costs were calculated for present conditions as well as both design conditions. <br /> Costs were also calculated for hauling cake biosolids versus liquid biosolids. <br /> Table 5.4 <br /> Preliminary Cost Estimates for Regionalization Biosolids Option <br /> Elk River Wastewater Treatment Facility <br /> Present Option 1 Option 2 <br /> Liquid Cake* Liquid Cake* Liquid Cake* <br /> Yearly Treatment Cost $558,000 $496,000 $2,202,000 $1,957,000 $2,818,000 $2,505,000 <br /> Yearly Hauling Cost $198,000 $37,000 $782,000 $147,000 $1,001,000 $188,000 <br /> Total Yearly Cost $756,000 1 $533,000 $2,984,000 $2,104,000 $3,819,000 $2,693,000 <br /> *Cake biosolids hauling would require the construction of a biosolids dewatering facility. <br /> City of Elk River—T12.104758 Page 30 <br /> Wastewater Treatment Facility Plan Prepared by Bolton&Menk,Inc. <br />