<br />rilmdcnJ-1 /;34 (Uw <br />~ri\. d. D, <br /> <br /> Jackson Place Schedule <br />ID Task Name Duration . Sta rt Finish Pre, Resource Names <br />1 SITE WORK 3 days Mon 7/10/06 Wed 7/12/06 <br />2 Fencing & Traffic Control 1 day Mon 7/10/06 Mon 7/10/06 <br />3 Utility disconnects & demo 2 days Tue 7/11/06 Wed 7/12/06 2 <br />4 <br />5 SURVEYING 1 day Tue 7/18/06 Tue 7/18/06 2 <br />6 Stake building corners 1 day Tue 7/18/06 Tue 7/18/06 15 <br />7 <br />8 SHORING 46 days Mon 7/24/06 Tue 9/26106 <br />9 Driye pilings 8 days Mon 7/24/06 Wed 8/2/06 23 <br />10 Installlaaaina & planking 5 days Thu 8/3/06 Wed 8/9/06 16S <br />11 Demo lagging & clanking 4 days Wed 9/20/06 Mon 9/25/06 18 <br />12 Pull shorina 1 day Tue 9/26/06 Tue 9/26/06 11 <br />13 <br />14 EXCAVATING 50 days Thu 7/13/06 Thu 9/21/06 3 <br />15 Demo, clear & grub 3 days Thu 7/13/06 Mon 7/17/06 <br />16 Excayate basement 6 days Thu 8/3/06 Thu 8/10/06 9 <br />17 Backfill elevator pit & stairwells 1 day Thu 8/24/06 Thu 8/24/06 47 <br />18 Backfill basement 4 days Thu 9/14/06 Tue 9/19/06 48 <br />19 Sand cushion 2 days Wed 9/20/06 Thu 9/21/06 18 <br />20 <br />21 <br />22 UTILITIES 57 days Wed 7/19/06 Fri 10/6/06 <br />23 Utility relocations 3 days Wed 7/19/06 Fri 7/21/06 6 <br />24 Sewer & water 3 days Wed 9/27/06 Fri 9/29/06 12 <br />25 Electrical service 3 days Mon 1 0/2/06 Wed 10/4/06 24 <br />26 Gas service 2 days Thu 10/5/06 Fri 10/6/06 25 <br />27 <br />28 CONCRETE & MASONRY 121 days Fri 8/11/06 Mon 2/5/07 <br />29 Pour footinas 5 days Fri 8/11/06 Thu 8/17/06 16 <br />30 Below-grade block 10 days Fri 8/18/06 Thu 8/31/06 29 <br />31 Stairwell slabs 1 day Fri 8/25/06 Fri 8/25/06 17 <br />32 Pour stair pans 1 day Wed 9/13/06 Wed 9/13/06 43 <br />33 Pour ramo walls 3 days Fri 9/1/06 Wed 9/6/06 30 <br />34 Pour ramo slab 4 days Fri 1 0/13/06 Wed 10/18/06 100 <br />35 Basement slabs 4 days Tue 10/3/06 Fri 1 0/6/06 112 <br />36 1 st floor elevator shaft & stair towers 4 days Tue 9/12/06 Fri 9/15/06 53 <br />37 2nd & 3rd floor elevator shaft 5 days Wed 9/20/06 Tue 9/26/06 54 <br />38 Erect scaffold for masonrv veneer 4 days Fri 12/1/06 Wed 12/6/06 67 <br />39 Masonry veneer 40 days Thu 1217106 Mon 2/5/07 38 <br />40 <br />41 STEEL 66 days Fri 9/8/06 Tue 12/12106 <br />42 Measure steel stairs (basement) 1 day F ri 9/8/06 Fri 9/8/06 52 <br />43 Fab & install steel stairs . 2 days Mon 9/11/06 Tue 9/12/06 42 <br />44 Ship's ladder installation 1 day Tue 12/12/06 Tue 12/12/06 84 <br />45 <br />46 WATERPROOFING 15 days Wed 8/23/06 Wed 9/13/06 <br />47 Wateroroof elevator oit 1 day Wed 8/23/06 Wed 8/23/06 30S <br />48 Waterproof & drain tile basement 4 days Fri 9/8/06 Wed 9/13/06 52 <br />49 <br />50 PRECAST CONCRETE 12 days Fri 9/1/06 Tue 9/19/06 <br />51 Basement orecast columns & beams 2 days Fri 9/1/06 Tue 9/5/06 30 <br />52 1 st floor precast plank 2 days Wed 9/6/06 Thu 9/7/06 51 <br />53 1 st floor orecast columns & beams 2 days Fri 9/8/06 Mon 9/11/06 52 <br />54 2nd floor precast plank 2 days Mon 9/18/06 Tue 9/19/06 36 <br />55 <br />56 FRAMING 87 days Wed 9/20/06 Thu 1/25/07 <br />57 1 st floor stairway framina 2 days Wed 9/20/06 Thu 9/21/06 54 <br />58 1 st floor curtain wall framina 5 days Wed 9/20/06 Tue 9/26/06 54 <br />59 1 st floor interior wall framing 4 days Wed 9/27/06 Mon 10/2/06 58 <br />60 2nd floor wall framina 8 days Tue 10/3/06 Thu 10/12/06 59 <br />61 2nd floor ioists & deckinQ 7 days Fri 10/13/06 Mon 10/23/06 60 <br />62 2nd floor stairway framing 2 days Wed 9/27/06 Thu 9/28/06 37 <br />63 3rd floor wall framing 8 days Tue 10/24/06 Thu 11/2/06 61 <br />64 Roof ioists 7 days Fri 11/3/06 Mon 11/13/06 63 <br />65 Cornice cantilever framina 3 days Tue 11/14/06 Thu 11/16/06 64 <br />66 Parapet & roof slope framing 5 days Fri11/17/06 Mon 11/27/06 65 <br /> Page 1 <br />