Laserfiche WebLink
TIMEFRAME <br />PROJECT: EAST HIGHWAY 10 AND/OR COUNTY ROAD 12 <br />CC orders Appraisals in July and receives information in September, 1995. <br />Fall, 1995 - CC continues to evaluate assessment districts, assessment rates, <br />the city's financial contribution and city's ability to "hold" assessments. <br />COMPREHENSIVE PLAN - CC to approve before the end of 1995 and this <br />plan includes the east Elk River municipal service district(s). <br />Winter, 1995/96 - CC makes tentative decisions on assessment district(s), <br />assessment rate(s), city's financial contribution, city's ability to "hold" <br />expenses and project construction timetable...decisions discussed during <br />January/February CIP worksessions. <br />Spring, 1996 - CC orders WWTP plant expansion ($5 million) and project is <br />completed in late 1997...it may be possible to bid this project in fall of 1995 in <br />• order to get the best bids possible. <br />Spring/summer, 1996 - CC and staff hold public informational meetings on <br />the East Highway 10 and/or County Road 12 project. CC orders the detailed <br />feasibility study for this project and calls for a public hearing on this trunk <br />sewer and water project. This timeframe also works for any commercial <br />project that would take place on the trailer court property. <br />Fall winter, 1996 -Trunk sewer and water project is ordered after the trunk <br />assessment appeals have been decided. <br />Winter, 1996/97 -Construction begins on East Highway 10 and/or Country <br />Road 12 trunk sewer and water project after the assessment appeals are <br />decided and the project is completed in 1998. <br />~'P ~~ <br />~- /" <br />~- <br />~u~ <br />u~ ~ ~~6 Grdz"') <br />__~ <br />~~~- ~ - <br />~ ~ N~ ~ ~~-~ ,~k~ <br />1 <br />PDK notes - 6/26/95 <br />