Laserfiche WebLink
At our 12-13-OS meeting, authorization was given to execute the power purchase <br />agreement between GRE & ERMU to purchase the output for the 4~h engine. A condition <br />of the power purchase agreement was to secure a qualifying facility status for our landfill <br />gas facility from FERC. Attached is our application to FERC to self certify as a <br />qualifying facility. The necessary air permits have also been secured. <br />With all of the above being completed, the project can now move ahead with a June 2006 <br />operation data. Due to Waste Management time constraints, we have purchased the <br />engine/generator form them for $396,909 plus freight to be delivered to meet our June <br />2006 start date. Had we not purchased their engine, which was the lowest price, delivery <br />would be 48 weeks from date of order. <br />