ELK RIVER CITY HALL COMPLEX EXPANSION <br />ELK RIVER, MINNESOTA <br /> PROJECT SCHEDULE <br /> CRITICAL DATES <br /> JANUARY 2, 2002 <br /> REVISED MARCH 1, 2002 <br /> <br />T U S H I E <br />MONTGOMERY <br />ARCHITECTS <br /> <br /> Requires Completion <br /> City, EDA, Date <br />ACTIVITY Utility <br /> Commission <br /> Action <br />City Council determines size and scope of project · CC January 14, 2002 <br />Complete Preliminary Project Design January 28, 2002 <br />Select Construction Manager ·CC January 28, 2002 <br />City Council authorizes TMA to proceed with design development ·CC January 28, 2002 <br />and construction documents Utility <br />Submit design drawings to Planning Commission for public review February, 2002 <br />and approval <br />Submit design drawings to City Council for public review and final · CC March, 2002 <br />design approval <br />Complete design development documents February 28, 2002 <br />Complete construction documents for Public Safety April 30, 2002 <br />Start bond proceeds for Public Safety Building · EDA May 10, 2002 <br />Complete public bidding process and award construction contracts · EDA May 13, 2002 <br />for Public Safety <br />Start Construction of Public Safety Building June 1,2002 <br />Complete construction documents for Utility Building addition April 30, 2002 <br />Complete public bidding process and award construction contracts · May 13, 2002 <br />For Utility Building addition Utility <br />Start construction of Utility Building addition June 1,2002 <br />Complete construction documents for City Hall renovation and April 30, 2002 <br />expansion <br />Complete public bidding process and award construction contracts · CC May 13, 2002 <br />For City Hall work (additions) <br />Start const'ruction of City Hall Building additions June 1,2002, <br />Remove existing City Hall furniture to be renovated for Public March 28, 2003 <br />Safety <br />Have rental furniture for City Hall in place - existing space only March 30, 2003 <br />Complete construction of Public Safety Building May 30, 2003 <br />Owner move-in to Public Safety Building June 1 - 16, 2003 <br />City Hall move-in to Utility and Attorney additions June 1 - 16, 2003 <br />Complete construction of Utility Building addition May 30, 2003 <br />Start construction on renovation of existing City Hall space June 17, 2003 <br />Purchase new furniture for City Hall space · CC October 13, 2003 <br />Complete construction of renovated Public Safety City Hall space December 31,2003 <br />Owner move-in to renovated Public Safety and City Hall space January 2 - 16, 2004 <br />Freshen up Utility Building space after City vacates Jan 17 - Feb 14, 2002 <br />Owner move-in to Utility addition space Feb 15 - 28, 2004 <br /> <br /> <br />