<br />TH 169 Elk River to Princeton <br />Estimated SRF Deliverable Dates <br /> <br />~ Project Management deliverables as identified in include meeting agendas, <br />meeting minutes, project status reports, presentation materials, handouts and <br />follow-up correspondence to coordinate work activities. (These will be <br />delivered on an ongoing basis throughout the study process). <br /> <br />~ Assembly of background information for corridor, development of GIS base <br />map showing existing issues, constraints and opportunities in the study area, <br />assembly of historic traffic and crash information, water resources overview map, <br />water resources regulatory matrix. Estimated deliverable date (April 2006). <br /> <br />62- SRF to document changes in layouts and rationale for changes; conduct <br />traffic analysis of alternatives, and document transportation purpose and need. <br />Information to be developed throughout 2006 with final traffic <br />memorandum delivered by December 2006. <br /> <br />2.3 Alternatives evaluation report documenting process, analysis, alternative <br />modifications, evaluation matrix and recommendations (January 2007). Seoping <br />meeting materials and follow-up meeting documentation (February 2007). <br />Benefit-cost memorandum (December 2006). <br /> <br />3.0 Draft/Final Noise Analysis, Tech Memo (September 2007), Noise <br />Exemption Request (October 2007), Draft /Final Wetlands Tech Memo <br />(September 2007); AD 1006 form, draft EA/EAW (November 2007), Final <br />EA/EAW, draft/final responses to comments (December 2007), Draft/Final <br />FONSI (May 2008). <br /> <br />4.0 Hydraulics letter, formulating ponding stage, locations and special water <br />quality treatment requirements (June 2007). <br /> <br />5.0 Coordination through meetings, emails, phone-calls and/or drawings for <br />preliminary design task (These to be delivered on an ongoing basis <br />throughout the study process). Final geometric staff approved layouts for <br />entire corridor (August 2007). Assistance and attendance at meetings with local <br />agencies to obtain municipal consent (September to December 2007). <br /> <br />6.0 Documentation of utility correspondence and contact list, placement of <br />utility information on geometric layouts (August 2006). <br /> <br />7.0 Public Involvement deliverables include meeting notices, materials, boards, <br />presentation materials, and meeting summaries for up to 22 LAC meetings and <br />