Laserfiche WebLink
City of Elk River Design Standards <br />Items Needed to Start Utility Construction <br />1. Site grading is completed. <br />2. Approved construction plan. <br />3. Approved construction specifications. <br />4. Hold preconstruction meeting. <br />5. SWPPP approved and signed. <br />6. NPDES permit for grading. <br />7. MPCA permit. <br />8. MDH water permit. <br />9. County access permit (if necessary). <br />10. Erosion con�sol is in place. <br />11. Developer's agreement has been executed. <br />12. Permit fees paid to City. <br />13. Surety posted with City. <br />14. Cost of Public Improvements provided to City broken down into 4 categories: <br />A. Sanitary sewer <br />B. Watermain <br />C. Storm sewer <br />D. Street construction <br />OO City of Elk River, Minnesota — All rights reserved 29 <br />