• Working on plans/staking for stage three of the County Road 35 overhead rebuild. We <br />will start setting poles later in December. <br />• Moved all equipment from the old shop to the new facility. I am still in the process of <br />moving from the old office building. <br />• Participated in administrations director interviews Monday, December 5. <br />• The deputy general manager along with staff from key accounts, electric, technical <br />services, engineering departments, and myself met with staff at a data center to talk <br />cabinet needs. They also gave us a tour of the facility. <br />• We finally received 20 single phase transformers this past Friday. <br />Page 2 of 2 <br />169 <br />