Laserfiche WebLink
Exhibit B <br />WSB will complete the Northeast Elk River Urban Service Expansion Study within 12 weeks of receiving authorization <br />to proceed from the City. WSB will coordinate project milestones and deliverables with Ehlers & Associates. An <br />estimated timeframe for completing the study includes the following approximate milestone dates and deliverables <br />for each phase: <br />ESTIMATED <br />COMPLETION DATE <br />DELIVERABLE <br />I <br />CITY AUTHORIZES PROPOSAL <br />FEBRUARY 7, 2022 <br />AGREEMENT <br />KICK OFF MEETING <br />FEBRUARY 15, 2D22 <br />MEETING AGENDA <br />COMPLETE DRAFT STUDY REPORT <br />APRIL 15, 2022 <br />PDF DRAFT STUDY REPORT AND <br />HARD COPIES AS REQUESTED <br />PROGRESS MEETING TO DISCUSS <br />APRIL 18, 2022 <br />MEETING AGENDA <br />DRAFT STUDY REPORT <br />PDF FINAL STUDY REPORT AND/ <br />COMPLETE FINAL STUDY REPORT <br />APRIL 29, 2022 <br />OR 429 FEASIBILITY STUDY <br />REPORT AND HARD COPIES AS <br />REQUESTED <br />