• <br /> Cost ' ecove Scenarios (cont'd) eRN <br /> Scenario E: Project Cancelled in 2016 <br /> Scenario E : 1 <br /> • Project completes construction through 2015, and is ready for <br /> in-service in early 2016. <br /> ® Project cancelled before plant goes in-service. <br /> ▪ Plant portion of project has no market (salvage value) . <br /> ▪ Transmission portion of project has 100% market value. <br /> And represents about 16% of total project cost. <br /> • ERMU must recover BSPII plant costs from utility customers. <br /> • ERMU must replace planned BSPII plant output with other <br /> resources.2 <br /> 1 . This is an extreme worst-case scenario. While possible, CMMPA views the probability of <br /> this Scenario occurring as remote. <br /> 2. Replacement resources assumed to be Connexus incremental costs, RW Beck study <br /> Case 1 B. <br /> 13 <br />