Expenditures and Amortization <br /> Phase 2: Construction* (Assumes 30 MW F.RMU Share) <br /> Project construction cost : $ 100 million <br /> Includes both plant and transmission . <br /> Includes the $3 . 4M development cost <br /> from Phase 1 . <br /> Interest During Construction <br /> • Interest on the $ 100M to 2016 in-service $23 million <br /> • To be included in bonding . <br /> Total capital cost <br /> To be recovered in rates during Phase 3 : $ 123 million <br /> * Assumes CMMPA does bond financing for all ERMU costs 17 <br /> and interest, at 5.5 /o interest rate. <br />