ME Terra
<br />CONSTRUCTION EXHIBIT 2
<br />21025 Commerce Blvd., Suite 1000
<br />Rogers, MN 55374
<br />Elk River Fire Station #3
<br />Bid Opening: January 21, 2021
<br />LOW BID SUMMARY
<br />BID CATEGORY
<br />LOW BIDS
<br />RECEIVED
<br />APPARENT LOW BIDDERS
<br />City of
<br />Bids
<br />Received
<br />NOTES
<br />Genl Reqmts, , Bonds, Ins, Personnel, Precon
<br />$810,829
<br />Excludes Permits & SAC/WAC - Included in Soft Costs
<br />BC#3A - Concrete
<br />$348,900
<br />Thomsen Construction Services
<br />13
<br />BC#3B - Polished Concrete
<br />$26,666
<br />Concrete Treatments
<br />6
<br />BC#4A-Masonry
<br />$1,115,000
<br />Carrico
<br />8
<br />BC#5A - Steel Supply
<br />$295,760
<br />Terra Recommends to Re -Bid
<br />1
<br />Only One Bidder - Recommend not awarding and Re -Bid
<br />BC#5B - Steel Install
<br />$117,750
<br />Patriot Erectors
<br />7
<br />BC#6A - Carpentry
<br />$243,000
<br />Century Construction
<br />7
<br />BC#6B - Casework
<br />$45,900
<br />Northern Woodwork
<br />4
<br />BC#7A - Roofing
<br />$149,000
<br />Horizon Roofing
<br />12
<br />BC#7B - Metal Roofing & Wall Panels
<br />$236,124
<br />Horizon Roofing
<br />10
<br />BC#7C - Fluid Applied Air Barrier
<br />$38,600
<br />Herzog Coatings
<br />5
<br />BC#7D - Joint Sealants
<br />$45,470
<br />Sunrise Specialty Contracting
<br />5
<br />BC#8A - Doors, Frames & Hardware (Material Only)
<br />$94,389
<br />Mid Central Door
<br />3
<br />BC#8B - Sectional Doors
<br />$89 987
<br />American Door Works
<br />6
<br />The low bidder (Dooroo) had an error and withdrew their bid
<br />BC#8C - Glass & Glazing
<br />$163,500
<br />Hallmark Glass
<br />7
<br />BC#9A - Gypsum Board
<br />$163,647
<br />Neimeal Design & Construction
<br />6
<br />BC#9B - Tile
<br />$49,815
<br />Tim's Construction Group
<br />8
<br />BC#9C - Acoustical Ceilings
<br />$89,350
<br />Sonus Interiors
<br />5
<br />BC#9D - Carpet & Resilient
<br />$19,500
<br />Centennial Flooring
<br />5
<br />BC#9E - Resinous Flooring
<br />$46,523
<br />Concrete Treatments
<br />4
<br />BC#9F- Painting & Wallcovering
<br />$76,200
<br />Steinbrecher Painting
<br />8
<br />BC#21A - Fire Suppression
<br />$47,600
<br />Summit Fire
<br />5
<br />BC#22A - Mechanical
<br />$922,000
<br />Peterson Sheetmetal
<br />16
<br />The low bidder (Liberty Plumbing) had multiple errors and withdrew their bid
<br />BC#26A - Electrical
<br />$464,400
<br />Klein Electric
<br />10
<br />BC#31A-Earthwork
<br />$174,465
<br />Dryden Excavating
<br />17
<br />BC#32A - Fencing
<br />$4 485
<br />Peterson Companies
<br />3
<br />BC#32B - Landscaping
<br />$68,500
<br />Autumn Ridge
<br />13
<br />BC#32C - Asphalt Paving
<br />$70,490
<br />Ohman Brothers
<br />5
<br />BC#32D - Curb, Gutter & Sidewalks
<br />$220,000
<br />Ultra Concrete
<br />6
<br />BC#33A- Site Utilities
<br />$184,949
<br />Dryden Excavating
<br />11
<br />SUB -TOTAL
<br />$6,422,799
<br />Total Bids Received:
<br />216
<br />Add Alternate #1: Water Main for Future Wellhouse
<br />$60,130
<br />Dryden Excavating
<br />Add Alternate #2: High Speed Doors
<br />$80,583
<br />American Door Works
<br />Sub -Total with Alternates
<br />$6,563,512
<br />CM Project Fee (1.55%)
<br />$101,734
<br />FS#3 Contingency
<br />$233,000
<br />TOTAL With Add Alternates
<br />$6,898,246