Laserfiche WebLink
SCHEDULE 3 - DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br />to <br />provide a final design and to install the protective measures required by the Area <br />EPS. The Area EPS will review and approve the design, the types of relays specified, <br />and the installation. Mutually agreed upon exceptions may at times be necessary and <br />desirable. It is strongly recommended that the Interconnection Customer obtain Area <br />EPS written approval prior to ordering protective equipment for parallel operation. <br />The Interconnection Customer will own these protective measures installed at their <br />facility. <br />(c) The Interconnection Customer shall obtain prior approval from the Area EPS for any revisions <br />to the specified relay calibrations. <br />C)Commissioning Testing <br />The following tests shall be completed by the Interconnection Customer. All of the required tests in <br />each section shall be completed prior to moving on to the next section of tests. The Area EPS <br />operator has the right to witness all field testing and to review all records prior to allowing the system <br />to be made ready for normal operation The Area EPS shall be notified, with sufficient lead time to <br />allow the opportunity for Area EPS personnel to witness any or all of the testing. <br />i)Pre-testing The following tests are required to be completed on the Generation System prior to <br />energization by the Generator or the Area EPS. Some of these tests may be completed in the factory if <br />no additional wiring or connections were made to that component. These tests are marked with a <br />(1) Grounding shall be verified to ensure that it complies with this standard, the NESC and the NEC. <br />(2) <br />protection, shall be tested to ensure correct polarity, ratio and wiring <br />(3) <br />removed where required. <br />(4) Breaker / Switch tests Verify that the breaker or switch cannot be operated with interlocks in <br />place or that the breaker or switch cannot be automatically operated when in manual mode. <br />Various Generation Systems have different interlocks, local or manual modes etc. The intent of <br />this section is to ensure that the breaker or switches controls are operating properly. <br />(5) * Relay Tests All Protective relays shall be calibrated and tested to ensure the correct operation <br />of the protective element. Documentation of all relay calibration tests and settings shall be <br />furnished to the Area EPS operator. <br />(6) Trip Checks - Protective relaying shall functionally tested to ensure the correct operation of the <br />complete system. Functional testing requires that the complete system is operated by the <br />injection of current and/or voltage to trigger the relay element and proving that the relay element <br />trips the required breaker, lockout relay or provides the correct signal to the next control <br />element. Trip circuits shall be proven through the entire scheme (including breaker trip) <br />For factory assembled systems, such as inverters the setting of the protective elements <br />may occur at the factory. This section requires that the complete system including the <br />wiring and the device being tripped or activated is proven to be in working condition <br />through the injection of current and/or voltage. <br />350 <br />