SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> testing procedure fails to address components of the technical requirements for <br /> interconnection. <br /> The Area EPS Operator shall send qualified personnel to the DER site to inspect the <br /> interconnection and witness the testing.Testing and inspection shall occur on a Business <br /> Day at a mutually agreed upon date and time.The Area EPS Operator may waive the <br /> right to witness the testing. <br /> 11.4. Interconnection Costs <br /> 11.4.1 Estimation of Interconnection Costs <br /> The Interconnection Customer shall pay for the actual cost of the <br /> Interconnection Facilities and Distribution Upgrades along with the Area EPS <br /> Operator's cost to commission the proposed DER system. An estimate of the <br /> interconnection costs shall be stated in the Uniform Contract or in the MMIA in <br /> Attachment II, Interconnection Facilities and Upgrades, as a detailed itemization <br /> of such costs. If Network Upgrades are required, the actual cost of the Network <br /> Upgrades, including overheads, shall be borne by the Interconnection Customer <br /> pursuant to the Transmission Provider and associated agreements. <br /> 11.4.2 Progressive Payment of Interconnection Costs <br /> The Area EPS Operator shall invoice the Interconnection Customer for the <br /> design, engineering, construction and procurement costs of the Interconnection <br /> Facilities and Upgrades described in the MMIA Attachment II, on a monthly <br /> basis, or other manner agreed upon by both Parties in the MMIA, or as described <br /> in the Uniform Contract.The Interconnection Customer shall pay each invoice <br /> within twenty-one (21) Business Days or as agreed to in the MMIA or Uniform <br /> Contract. <br /> 11.4.3 Final Accounting of Interconnection Facilities and Upgrade Costs <br /> If distribution or transmission facilities required upgrades to accommodate the <br /> proposed DER system, the Area EPS Operator shall render the final <br /> interconnection cost invoice to the Interconnection Customer within eighty (80) <br /> Business Days (approximately four calendar months) of completing the <br /> construction and installation of the Area EPS Operator's Interconnection Facility <br /> and Upgrades. The Area EPS Operator shall provide the Interconnection <br /> Customer with a final accounting report identifying the difference between the <br /> actual Interconnection Customer's cost responsibility and the Interconnection <br /> Customer's previous aggregate payments to the Area EPS Operator for the <br /> specific DER system interconnection. Upon the final accounting submitted to the <br /> Interconnection Customer, the balance between the actual cost and previously <br /> 14 <br /> 216 <br />