Laserfiche WebLink
SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> 10.2. Timelines <br /> Within ten (10) Business Days of receipt of the proposed modification, the Area EPS <br /> Operator shall evaluate whether the proposed modification to the Interconnection <br /> Application constitutes a Material Modification. The definition in the Section 13 Glossary <br /> of the Process Overview document includes examples of what does and does not <br /> constitute a Material Modification. <br /> The Area EPS Operator shall notify the Interconnection Customer in writing of the final <br /> determination of the proposed modification. For proposed modifications that are <br /> determined to be a Material Modification the Interconnection Customer may choose to <br /> either: 1) withdraw the proposed modification; or 2) proceed with a new <br /> Interconnection Application.The Interconnection Customer shall provide its choice in <br /> writing to the Area EPS Operator within ten (10) Business Days after being provided the <br /> Material Modification determination. If the Interconnection Customer does not provide <br /> its choice within the timeline, the Interconnection Application shall be considered <br /> withdrawn. <br /> If the proposed modification is not determined to be a Material Modification, then the <br /> Area EPS Operator shall notify the Interconnection Customer in writing that the <br /> modification has been accepted and the Interconnection Customer shall retain its <br /> eligibility for interconnection, including its position in the queue. <br /> 11 Interconnection <br /> 11.1. Interconnection Milestones <br /> For DER systems that are not a qualifying facility less than 40 kW AC, the <br /> Interconnection Customer and the Area EPS Operator shall agree on milestones for <br /> which each Party is responsible and list them in Attachment IV in the Interconnection <br /> Agreement. To the greatest extent possible, the Parties will identify all design, <br /> procurement, installation and construction requirements associated with the project <br /> while also clearly identifying associated timelines, at the beginning, or as early within <br /> the process as possible, of the design, procurement, installation and construction phase. <br /> A Party's obligation under this provision may be extended by agreement. If a Party <br /> anticipates that they will be unable to meet a milestone for any reason other than a <br /> Force Majeure Event, they shall immediately notify the other Party of the reason(s) for <br /> not meeting the milestone, then propose the earliest reasonable alternative date in <br /> which this and future milestones will be met and request appropriate amendments to <br /> the Interconnection Agreement and its attachments. The Party affected by the failure to <br /> meet a milestone shall not unreasonably withhold agreement to such an amendment <br /> unless: <br /> 12 <br /> 214 <br />