SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> the two sides of the 240-volt service of more than 20%of the nameplate rating <br /> of the service transformer. <br /> The technical screens listed shall not preclude the Area EPS Operator from using tools <br /> that perform screening functions using different methodologies provided the analysis is <br /> targeted to maintain the voltage, thermal and protection objectives as the listed <br /> screen. <br /> 3.3. Notification of Approval of Application <br /> Provided the Interconnection Application passes the initial screens, or if the proposed <br /> interconnection fails the screens but the Area EPS Operator determines that the DER <br /> may nevertheless be interconnected consistent with safety, reliability and power <br /> quality standards, the Area EPS Operator shall provide notice to the Interconnection <br /> Customer that their Interconnection Application has been approved. The Area EPS <br /> Operator shall provide the Interconnection Customer with an Interconnection <br /> Agreement as outlined in Section 5. <br /> 3.4. Failure of Review Screens <br /> If the proposed interconnection fails the screens, and the Area EPS Operator does not <br /> or cannot determine from the Initial Review that the DER may nevertheless be <br /> interconnected consistent with safety, reliability, and power quality standards, unless <br /> the Interconnection Customer is willing to consider minor modifications or further <br /> study, the Area EPS Operator shall provide the Interconnection Customer the <br /> opportunity to attend a customer options meeting. <br /> The Area EPS Operator shall notify the Interconnection Customer of the determination <br /> and provide copies of all directly pertinent data and analyses underlying its conclusion, <br /> subject to confidentiality provisions in Section 12.1 of the Overview Process document. <br /> 3.5. Customer Options Meeting <br /> Within ten (10) Business Days of the Area EPS Operator's notification to the <br /> Interconnection Customer of the proposed interconnection's failure of the engineering <br /> screens, the Area EPS Operator and the Interconnection Customer shall schedule a <br /> customer options meeting to review possible facility modification, screen analysis and <br /> related results to determine what further steps are needed to permit the DER to be <br /> interconnected safely and reliably to the Distribution System. At the customer options <br /> meeting the Area EPS Operator shall: <br /> • Offer to perform a supplemental review in accordance with Section 4 and <br /> provide a non-binding good faith estimate of the cost of such review; or <br /> 6 <br /> 186 <br />