Laserfiche WebLink
SCHEDULE 3-DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCESS <br /> Uniform Contract—the Area EPS Operator's Agreement for Cogeneration and Small Power <br /> Production Facilities (Uniform Contract) that may be applied to all qualifying new and existing <br /> interconnections between the Area EPS Operator and a DER system having capacity less than <br /> 40 kilowatts. <br /> Upgrades—The required additions and modifications to the Area EPS Operator's Transmission <br /> or Distribution System at or beyond the Point of Interconnection. Upgrades may be Network <br /> Upgrades or Distribution Upgrades. Upgrades do not include Interconnection Facilities. <br /> 24 <br /> 159 <br />