Laserfiche WebLink
• June <br /> • USACE permit issued. <br /> • MPCA 401 Water Quality Certification completed. <br /> • Bids presented to City Council and Assessment Hearing ordered on 6/1/98. <br /> • Assessment Hearing Held on 6/29/98 - (30 day appeal period). <br /> • DNR, Protected Waters permit issued <br /> July <br /> • MPCA SDS permit issued. <br /> • Special Projects and Challenge Grants awarded. <br /> August <br /> • City Council awards contract on 8/3/98. <br /> • Lake is drained early in the month. <br /> • Start construction on 8/17/98. <br /> September <br /> • October <br /> • Project completed by 10/31/98. <br /> • <br /> clkriver\sys\shrdoc`.bgz\stever\lakoagda.doc <br />