Laserfiche WebLink
FIGURE #2 <br /> • LAKE ORONO IMPROVEMENT PROJECT TIME LINE <br /> January 1998 <br /> • Determination of wetlands on disposal sites, with property owner's <br /> permission, by Natural Resources Conservation Service (NRCS). <br /> • January 7 meeting with permitting governmental agencies. <br /> • Preliminary assessment role (equivalency units) by January 15 meeting. <br /> • State Disposal Systems permit (SDS) submitted to the Minnesota <br /> Pollution Control Agency (MPCA) - (180 days). <br /> • Funding from Sherburne County sought. <br /> February <br /> • Protected Waters permit submitted to the Minnesota Department of <br /> Natural Resources (DNR) - (45 days). <br /> • U.S. Army Corps of Engineer (USACE) permit submitted - (60 to 120 <br /> days). <br /> • 401 Water Quality Certification submitted to MPCA - (60-120 days). <br /> • Environmental Assessment Worksheet (EAW) submitted to appropriate <br /> agencies - (approximately 60 days). <br /> • National Pollutant Discharge Elimination System <br /> • +-+permit (NPDES) submitted to MPCA - (permit immediate after <br /> submittal). <br /> • Feasibility Study ordered by the City Council on 2/16/98. <br /> March <br /> • Feasibility received by City Council and Public Hearing ordered on 3/2/98. <br /> April <br /> • Public Hearing held and plans and specifications ordered by City Council <br /> on 4/13/98. <br /> • Special Projects and Challenge Grant applications to repair erosion at <br /> Orono Cemetery submitted. <br /> May <br /> • Plans and Specifications approved and bids authorized by the City <br /> Council on 5/4/98. <br /> • Bids advertised for 21 days. <br /> • EAW process is completed. <br /> S <br /> \\elkriver\sys\shrdoc\b&z\stever\lakoagda.doc <br />