= Architectural Group Ltd.
<br /> 15 Groveland Terrace - Minneapolis, MN 55403-1 1 54
<br /> Telephone 612.377.2737 • Facsimile 612.377.1 331
<br /> E-Mail archcmkodet.com • Website www.kodet.com
<br /> March 26,2018
<br /> Mr.Zack Carlton
<br /> City of Elk River-Planning Manager
<br /> 13065 Orono Parkway
<br /> Elk River, MN 55330
<br /> Re: Elk River Jackson Street Historic Water Tower- Renovation
<br /> Dear Mr.Carlton:
<br /> We have evaluated the existing water tower and generated budgeting numbers to help
<br /> assist you in the grant submission. The existing water tower was scanned by a UAV(Unmanned Aerial Vehicle)on
<br /> February 81h,2018. We have taken the data from the scan and converted it into a scaled drawing which was used for cost
<br /> estimating by two painting contractors. Both painting contractors have separated out their cost estimate into three options as
<br /> noted below. Each of the three options give you different levels of restoration to choose from:
<br /> 1. Option 1 (short term)-pressure wash water tower and repaint. Fix structural items as noted in report dated August
<br /> 3,2015.
<br /> 2. Option 2(medium term)-pressure wash and sand blast only problem areas as identified in report and repaint. Fix
<br /> structural items as noted in report dated August 3,2015.
<br /> 3. Option 3 (Long term)-remove all the lead base paint by sand blasting the entire water tower and repaint. Fix
<br /> structural items as noted in report dated August 3,2015.
<br /> The two attached cost estimates from the painting contractors did not include the
<br /> following mark-ups-25%Soft Costs,20%for contingency and 10%per year for inflation-see cost breakouts below.
<br /> Estimate / Soft Costs(25%) / Contingency(20%) / 2018 cost / 2019 cost(10%) /2020 cost(10%)
<br /> 1.Slack Painting:
<br /> a.Option 1 - $92,000 + $23,000 + $18,400 =$133,400 $146,740 $161,414
<br /> b.Option 2- $130,000 + $32,500 + $26,000 =$188,500 $207,350 $228,085
<br /> c.Option 3 - $390,000 + $97,500 + $78,000 = $565,500 $622,050 $684,255
<br /> 2.TMI Coating:
<br /> a.Option 1 - $153,000 + $38,250 + $30,600 =$221,850 $244,035 $268,439
<br /> b.Option 2- $193,000 + $48,250 + $38,600 =$279,850 $307,835 $338,619
<br /> c.Option 3 - $385,000 + $96,250 + $77,000 =$558,250 $614,075 $675.483
<br /> Mr. Carlton,we again appreciate the opportunity to work with you and everyone with
<br /> the City of Elk River on this project. Let us know if you need additional information for the grant submission. If you have
<br /> any questions,please contact me.
<br /> Sincerely,
<br /> K ET AR HITECTURAL GROUP, LTD.
<br /> dward J. Kc et,Jr., FAIR, ED AP BD+C
<br /> Attachments:
<br /> Existing Drawing
<br /> TMI and Slack painting proposals
<br /> Architecture • Interiors - Planning
<br />
|