Laserfiche WebLink
SCHEDULE 3—INTERCONNECTION PROCESS,TECHNICAL REQUIREMENTS,AND OPERATING PROCEDURES <br /> (7)Remote Control, SCADA and Remote Monitoring tests—All remote control functions and remote <br /> monitoring points shall be verified operational. In some cases, it may not be possible to verify all <br /> of the analog values prior to energization.Where appropriate,those points may be verified during <br /> the energization process <br /> (8)Phase Tests—the Interconnection Customer shall work with the Area EPS operator to complete <br /> the phase test to ensure proper phase rotation of the Generation and wiring. <br /> (9)Synchronizing test — The following tests shall be done across an open switch or racked out <br /> breaker. The switch or breaker shall be in a position that it is incapable of closing between the <br /> Generation System and the Area EPS for this test.This test shall demonstrate that at the moment <br /> of the paralleling-device closure, the frequency, voltage and phase angle are within the required <br /> ranges, stated in IEEE 1547. This test shall also demonstrate that is any of the parameters are <br /> outside of the ranges stated; the paralleling-device shall not close. For inverter-based <br /> interconnected systems this test may not be required unless the inverter creates fundamental <br /> voltages before the paralleling device is closed. <br /> ii) On-Line Commissioning Test — the following tests will proceed once the Generation System has <br /> completed Pre-testing and the results have been reviewed and approved by the Area EPS operator. For <br /> smaller Generation Systems the Area EPS may have a set of standard interconnection tests that will be <br /> required. On larger and more complex Generation Systems the Interconnection Customer and the Area <br /> EPS operator will get together to develop the required testing procedure. All on-line commissioning <br /> tests shall be based on written test procedures agreed to between the Area EPS operator and the <br /> Interconnection Customer. <br /> Generation System functionally shall be verified for specific interconnections as follows: <br /> (1)Anti-Islanding Test—For Generation Systems that parallel with the utility for longer than 100msec. <br /> (a)The Generation System shall be started and connected in parallel with the Area EPS source <br /> (b)The Area EPS source shall be removed by opening a switch, breaker etc. <br /> (c)The Generation System shall either separate with the local load or stop generating <br /> (d)The device that was opened to remove the Area EPS source shall be closed and the <br /> Generation System shall not re-parallel with the Area EPS for at least 5 minutes. <br /> iii) Final System Sign-off. <br /> (1)To ensure the safety of the public, all interconnected customer owned generation systems which <br /> do not utilize a Type-Certified system shall be certified as ready to operate by a Professional <br /> Electrical Engineer registered in the State of Minnesota, prior to the installation being considered <br /> ready for commercial use. <br /> iv) Periodic Testing and Record Keeping <br /> Interconnection Process for Distributed Generatte(roSystems <br />