SCHEDULE 3—INTERCONNECTION PROCESS,TECHNICAL REQUIREMENTS,AND OPERATING PROCEDURES <br /> GENERAL INFORMATION <br /> A) Definitions <br /> 1) "Applicant" is defined as the person or entity who is requesting the interconnection of the <br /> Generation System with the Area EPS and is responsible for ensuring that the Generation <br /> System is designed, operated and maintained in compliance with the Technical <br /> Requirements. <br /> 2) "Area EPS" is defined as an electric power system (EPS) that serves Local EPS's. Note. <br /> Typically, an Area EPS has primary access to public rights-of-way, priority crossing of <br /> property boundaries,etc. <br /> 3) "Area EPS Operator"is the entity who operates the Area EPS. <br /> 4) "Dedicated Facilities" is the equipment that is installed due to the interconnection of the <br /> Generation System and not required to serve other Area EPS customers. <br /> 5) "Distribution System" is the Area EPS facilities which are not part of the Area EPS <br /> Transmission System or any Generation System. <br /> 6) "Extended Parallel" means the Generation System is designed to remain connected with the <br /> Area EPS for an extended period of time. <br /> 7) "Generation" is defined as any device producing electrical energy, i.e., rotating generators <br /> driven by wind, steam turbines, internal combustion engines, hydraulic turbines, solar, fuel <br /> cells,etc.;or any other electric producing device,including energy storage technologies. <br /> 8) "Generation Interconnection Coordinator" is the person or persons designated by the Area <br /> EPS Operator to provide a single point of coordination with the Applicant for the generation <br /> interconnection process. <br /> 9) "Generation System" is the interconnected generator(s), controls, relays, switches, <br /> breakers, transformers, inverters and associated wiring and cables, up to the Point of <br /> Common Coupling. <br /> 10) "Interconnection Customer" is the party or parties who will own/operate the Generation <br /> System and are responsible for meeting the requirements of the agreements and Technical <br /> Requirements. This could be the Generation System applicant, installer, owner, designer, or <br /> operator. <br /> 11) "Local EPS" is an electric power system (EPS) contained entirely within a single premises or <br /> group of premises <br /> 12) "Nameplate Capacity" is the total nameplate capacity rating of all the Generation included in <br /> the Generation System. For this definition the"standby"and/or maximum rated kW capacity <br /> on the nameplate shall be used. <br /> 13) "Open Transfer" is a method of transferring the local loads from the Area EPS to the <br /> generator such that the generator and the Area EPS are never connected together. <br /> Interconnection Process for Distributed Generate Systems <br />