Laserfiche WebLink
January 16, 2018 <br /> Elk River Ice Arena—Milestone Schedule <br /> Pre-Construction <br /> • Schematic Design Complete January 15 <br /> • Discuss Project Milestones with Council January 16 <br /> (Includes timeline for project financing/repayment, rental revenue) <br /> • Retail Space Work Session with Council January 16 <br /> • Schematic Design Estimate (3 weeks) January 15-February 2 <br /> • Meet w/Team to Review Estimate February 5 <br /> • Rental Revenue (Arena, Rec. Facilities and Fields)with Council February 5 <br /> • Finalize Softball Field Relocation with Council February 5 <br /> • Project Financing discussion with Council February 19 <br /> • Design Development Complete February 23 <br /> • Design Development Estimate (3 weeks) February 23-March 16 <br /> • Meet w/Team to Review Estimate March 19 <br /> • Approval of Design/Advertise for Bid Package 1 (BPI) by Council March 19 <br /> • Issue BPI (Precast)Advertisement to Bid March 20 <br /> • Issue BPI Bid Documents March 23 <br /> • Issue 95%CD Documents March 23 <br /> • BPI Bid Period (3.5 weeks) March 20-April 12 <br /> • 95%CD Estimate (3.5 weeks) March 20-April 12 <br /> • Award BPI by Council April 16 <br /> • Approval to Advertise for BP2 (Arena) by Council April 16 <br /> • Issue BP2 Advertisement to Bid April 17 <br /> • Construction Documents Complete April 27 <br /> • BP2 Bid Period (4 weeks) April 27-May 24 <br /> • Bid Opening May 24 <br /> • RJM Assembly of Final Bids May 24-June 4 <br /> • Award BP2 by Council June 4 <br /> • Construction Start June 11 <br />