• Schematic Design Complete January 15 <br /> • Discuss Project Milestones with Council January 16 <br /> (Includes timeline for project financing/repayment, rental revenue) <br /> • Retail Space Work Session with Council January 16 <br /> • .Schematic Design Estimate (3 weeks) January 15-February 2 <br /> • Meet w/Team to Review Estimate February 5 <br /> • Rental Revenue (Arena, Rec. Facilities and Fields) with Council February 5 <br /> • Finalize Softball Field Relocation with Council February 5 <br /> • Project Financing discussion with Council February 19 <br /> • Design Development Complete February 23 <br /> • Design Development Estimate (3 weeks) February 23-March 16 <br /> • Meet w/ Team to Review Estimate March 19 <br /> • Approval of Design/Advertise for Bid Package 1 (BP1) by Council March 11) <br /> • Issue 13P1 (Precast) Advertisement to Bid March 20 <br /> City of <br /> El <br /> W <br />