<br /> <br />Elk River Ice Arena Milestone Schedule <br />The following schedule was put together with the assistance of RJM Construction. To be able to start <br />construction in the spring (2018), the project will need to bid by February 1, 2018. This will require an <br />accelerated design schedule, completing the design work in 4.5 months instead of 6 months for a <br />project of this scope. <br />Milestone Schedule <br /> Pre-Construction <br />· Start Project September 15, 2017 <br />· Schematic Design Sept. 15 – Nov 1, 2017 <br />· Design Development Nov. 2 – Dec. 7, 2017 <br />· Constructions Documents Dec. 8 – Feb. 1, 2018 <br />· Bid Period (4 weeks) Feb 2 – March 1, 2018 <br />· Bid Opening March 1, 2018 <br />· Meet w/Team to Review Bids March 8, 2018 <br />· Precast Procurement Start (16 Weeks) March 16, 2018 <br />Construction <br />· Construction Start April 17, 2018 <br />· Mobilization/Demo/Foundations April 17 – July 9, 2018 <br />· Precast/Structural Steel July 10 – Aug 20, 2018 <br />· Roofing Complete September 11, 2018 <br />· Ready for Refrigeration Equipment October 25, 2018 <br />· Ready to Make Ice-Rink Addition February 14, 2019 <br />· Substantial Completion - Rink Addition February 14, 2019 <br />· Rink Renovation Start January 31, 2019 <br />· Demo Complete-Rink Renovation February 27, 2019 <br />· Rink Renovation Completion June 13, 2019 <br />End of Project <br /> <br />