SECTION 00991— CHANGE ORDER <br />PROJECT: WWTF Improvements <br />DATE OF ISSUANCE: 7/6/2016 <br />OWNER: City of Elk River, Minnesota <br />ENGINEER'S Project No.: T21.106811 <br />EFFECTIVE DATE: 7/6/2016 <br />No. 2 <br />CONTRACTOR: Rice Lake Const. Group ENGINEER: Bolton & Menk, Inc. <br />You are directed to make the following changes in the Contract Documents. <br />Description: <br />The Contractor experienced delays with establishing the correct microbiology in the aeration basins and it took nine (9) <br />weeks for the Contractor to establish the correct microbiology to produce good biologic treatment. Typically it takes <br />approximately four (4) weeks to establish the correct microbiology. <br />Reason for Change Order: <br />The aeration basins were started during the winter (December 2015) and the cold weather inhibited the microorganisms <br />from growing quickly causing the extra time. <br />Attachments: (List documents supporting change) <br />See attached letter from Rice Lake Construction Group dated <br />May 3, 2016. <br />CHANGE IN CONTRACT PRICE: <br />CHANGE IN CONTRACT TIMES: <br />Original Contract Price <br />Original Contract Times <br />Substantial Completion :740 days or dates <br />$16,525,200.00 <br />Ready for final payment :700 days or dates <br />Net changes from previous Change Orders No. 1 to No. 1 <br />Net changes from previous Change Orders No.1 to No. l <br />$16,785,191.59 <br />138 days <br />Contract Price Prior to this Change Order <br />Contract Times prior to this Change Order <br />Substantial Completion :838 days or dates <br />$16,785,191.59 <br />Ready for final payment :838 days or dates <br />Net Increase of this Change Order <br />Net Increase of this Change Order <br />$0.00 <br />35 days <br />Contract Price with all approved Change Orders <br />Contract Times with all approved Change Orders <br />Substantial Completion :873 days or dates <br />$16,785,191.59 <br />Ready for final payment :873 days or dates <br />RECOMMENDED: A—? J <br />By: <br />Engineer (Authorized Signature) <br />Dake: 7/6/2016 <br />EJCDC No. 191008-13 (1990 Edition) <br />APPROVED: <br />By: <br />Owner (Authorized Signature) <br />ACCEP7D: <br />By: <br />Contractor (Authorized Signature) <br />7A Itr, <br />Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America. <br />T21.106811 — Elk River, MN CHANGE ORDER <br />Wastewater Treatment Facility Improvements PAGE 00991-1 <br />