GENERAL NOTES:
<br />1. THECONTRACTOR SHALL INSPECT THE SITE AND BECOME
<br />FAMILIAR WITH THEEXISTING CONDITIONS RELATING TO
<br />THE NATURE AND SCOPE OF THE WORK.
<br />2. THE CONTRACTOR SHALL VERIFY PLAN LAYOUT AND BRING
<br />TO THE ATTENTION OF THE LANDSCAPE ARCHITECT
<br />DISCREPANCIES WHICH MAY COMPROMISE THE DESIGN OR
<br />INTENTOF THE LAYOUT.
<br />3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
<br />COMPLYING WITH ALL APPLICABLE CODES, REGULATIONS,
<br />AND PERMITS GOVERNING THE WORK.
<br />4. THE CONTRACTOR SHALL PROTECT EXISTING ROADS,
<br />CURBS/GUTTERS, TRAILS, TREES, LAWNS AND SITE
<br />ELEMENTS DURING CONSTRUCTION. DAMAGE TO SAME
<br />SHALLBE REPAIRED AND/OR REPLACED AT NO
<br />ADDITIONAL COST TO THE OWNER.
<br />5. LOCATE AND VERIFY ALL UTILITIES, INCLUDING IRRIGATION
<br />LINES, WITH THE OWNER FOR PROPRIETARY UTILITIES AND
<br />GOPHER STATE ONE CALL 48 HOURS BEFORE DIGGING.
<br />CONTRACTOR SHALL BE RESPONSIBLE FOR THE
<br />PROTECTION AND REPAIR OF ANY DAMAGES TO SAME.
<br />NOTIFY THE LANDSCAPE ARCHITECT OF ANY CONFLICTS TO
<br />FACILITATE PLANT RELOCATION.
<br />6. THE CONTRACT SHALL COORDINATE THE PHASES OF
<br />CONSTRUCTION AND PLANTING INSTALLATION WITH OTHER
<br />CONTRACTORS WORKING ON SITE,
<br />7, THE CONTRACTOR SHALL REVIEW THE SITE FOR
<br />DEFICIENCIES IN SITE CONDITIONS WHICH MIGHT
<br />NEGATIVELY AFFECT PLANT ESTABLISHMENT, SURVIVAL OR
<br />WARRANTY. UNDESIRABLE SITE CONDITIONS SHALL BE
<br />BROUGHT TO THE ATTENTION OF THE LANDSCAPE
<br />ARCHITECT PRIOR TO BEGINNING OF WORK.
<br />8. THE PLAN TAKES PRECEDENCE OVER THE LANDSCAPE
<br />LEGEND IF DISCREPANCIES EXIST. QUANTITIES SHOWN IN
<br />THE PLANTING SCHEDULE ARE FOR THE CONTRACTOR'S
<br />CONVENIENCE. CONTRACTOR TO VERIFY QUANTITIES SHOWN
<br />ON THE PLAN.
<br />9. THE SPECIFICATIONS TAKE PRECEDENCE OVER THE
<br />PLANTING NOTES AND GENERAL NOTES.
<br />10. EXISTING TREES AND SHRUBS TO REMAIN SHALL BE
<br />PROTECTED TO THE DRIP LINE FROM ALL CONSTRUCTION
<br />TRAFFIC, STORAGE OF MATERIALS ETC. WITH 4' HT.
<br />ORANGE PLASTIC SAFETY FENCING ADEQUATELY
<br />SUPPORTED BY STEEL FENCE POSTS 6' O.C. MAXIMUM
<br />SPACING.
<br />11. LONG-TERM STORAGE OF MATERIALS OR SUPPLIES
<br />ON-SITE WILL NOT BE ALLOWED.
<br />12. CONTRACTOR SHALL REQUEST IN WRITING, A FINAL
<br />ACCEPTANCE INSPECTION.
<br />PLANTING NOTES:
<br />1, NO PLANTS SHALL BE INSTALLED UNTIL FINAL GRADING
<br />AND CONSTRUCTION HAS BEEN COMPLETED IN THE
<br />IMMEDIATEAREA.
<br />2, ALL PLANTING STOCK SHALL CONFORM TO THE "AMERICAN
<br />STANDARD FOR NURSERY STOCK," ANSI -Z60, LATEST
<br />EDITION. OF THE AMERICAN ASSOCIATION OF
<br />NURSERYMEN, INC. AND SHALL CONSTITUTE MINIMUM
<br />QUALITY REQUIREMENTS FOR PLANT MATERIALS.
<br />3, OVERSTORY TREES SHALL BEGIN BRANCHING NO LOWER
<br />THAN 6' ABOVE PAVED SURFACES.
<br />4. ALL PLANTS MUST BE HEALTHY, VIGOROUS MATERIAL,
<br />FREE OF PESTS AND DISEASE AND BE CONTAINER GROWN
<br />OR BALLED AND BURLAPPED AS INDICATED IN THE
<br />LANDSCAPE LEGEND.
<br />5. PLANT MATERIALS TO BE INSTALLED PER PLANTING
<br />DETAILS.
<br />6. ALL TREES MUST BE STRAIGHT TRUNKED AND FULL
<br />HEADED AND MEET ALL REQUIREMENTS SPECIFIED.
<br />7, THE LANDSCAPE ARCHITECT RESERVES THE RIGHT TO
<br />REJECT ANY PLANTS WHICH ARE DEEMED UNSATISFACTORY
<br />BEFORE. DURING, OR AFTER INSTALLATION.
<br />8, NO SUBSTITUTIONS OF PLANT MATERIAL SHALL BE
<br />ACCEPTED UNLESS APPROVED IN WRITING BY THE
<br />LANDSCAPE ARCHITECT.
<br />9. ALL PLANT MATERIAL QUANTITIES, SHAPES OF BEDS AND
<br />LOCATIONS SHOWN ARE APPROXIMATE. CONTRACTOR
<br />SHALL BE RESPONSIBLE FOR COMPLETE COVERAGE OF
<br />ALL PLANTING BEDS AT SPACING SHOWN AND ADJUSTED
<br />TO CONFORM TO THE EXACT CONDITIONS OF THE SITE
<br />THE LANDSCAPE ARCHITECT SHALL APPROVE THE STAKING
<br />LOCATION OF ALL PLANT MATERIALS PRIOR TO
<br />INSTALLATION.
<br />10, ALL PLANTING AREAS MUST BE COMPLETELY MULCHED AS
<br />SPECIFIED.
<br />11, MULCH: SHREDDED HARDWOOD MULCH, CLEAN AND FREE
<br />OF NOXIOUS WEEDS OR OTHER DELETERIOUS MATERIAL,
<br />IN ALL MASS PLANTING BEDS AND FOR TREES, UNLESS
<br />INDICATED AS ROCK MULCH ON DRAWINGS. SUBMIT
<br />SAMPLE TO LANDSCAPE ARCHITECT PRIOR TO DELIVERY
<br />ON-SITE FOR APPROVAL DELIVER MULCH ON DAY OF
<br />INSTALLATION. USE 4" FOR SHRUB BEDS, AND 3"FOR
<br />PERENNIAL/GROUND COVER BEDS, UNLESS OTHERWISE
<br />DIRECTED.
<br />12. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL
<br />MULCHES AND PLANTING SOIL QUANTITIES TO COMPLETE
<br />THEWORK SHOWN ON THE PLAN.
<br />13. USE ANTIDESICCANT(WILTPRUF OR APPROVED EOUAL)
<br />ON DECIDUOUS PLANTS MOVED IN LEAF AND FOR
<br />EVERGREENS MOVED ANYTIME. APPLY AS PER
<br />MANUFACTURER'S INSTRUCTION. ALL EVERGREENS SHALL
<br />BE SPRAYED IN THE LATE FALL FOR WINTER PROTECTION
<br />DURING WARRANTY PERIOD.
<br />14, PLANTING SOIL FOR TREES, SHRUBS AND GROUND
<br />COVERS: FERTILE FRIABLE LOAM CONTAINING A LIBERAL
<br />AMOUNT(49 MIN.) OF HUMUS AND CAPABLE OF
<br />SUSTAINING VIGOROUS PLANT GROWTH. IT SHALL
<br />COMPLY WITH ROBOT SPECIFICATION 3877 TYPE B
<br />SELECT TOPSOIL. MIXTURE SHALL BE FREE FROM
<br />HARDTACK SUBSOIL, STONES, CHEMICALS, NOXIOUS
<br />WEEDS, ETC. SOIL MIXTURE SHALL HAVE A PH BETWEEN
<br />6.1 AND 7.5 AND 10-0-10 FERTILIZER AT THE RATE OF
<br />3 POUNDS PER CUBIC YARD. IN PLANTING BEDS
<br />INCORPORATE THIS MIXTURE THROUGHOUT THE ENTIRE
<br />BED IN A 6' LAYER AND ROTO -TILLING IT INTO THE TOP
<br />12" OF SOIL AT A 1:1 RATIO.
<br />15, A Y PLANT SOCK NOT PLANTED ON DAY OF DELIVERY
<br />SHALL BE HEELED IN AND WATERED UNTIL INSTALL TION.
<br />PLANTS NOT MAINTAINED IN THIS MANNER WILL BE
<br />REJECTED.
<br />16. ALL PLANTS SHALL BE GUARANTEED FOR TWO COMPLETE
<br />GROWING SEASON (APRIL 1 - NOVEMBER1), UNLESS
<br />OTHERWISE SPECIFIED. THE GUARANTEE SHALL COVER
<br />THE FULL COST OF REPLACEMENT INCLUDING LABOR AND
<br />PLANTS.
<br />17, CONTRACTOR SHALL NOTIFY THE LANDSCAPE ARCHITECT
<br />AT LEAST 3 DAYS PRIOR TO PLANNED DELIVERY. THE
<br />CONTRACTOR SHALL NOTIFY THE LANDSCAPE ARCHITECT
<br />AT LEAST24 HOURS IN ADVANCE OF BEGINNING PLANT
<br />INSTALLATION.
<br />18. SEASONS/TIME OF PLANTING AND SEEDING: NOTE:
<br />THE CONTRACTOR MAY ELECT TO PLANT IN OFF-SEASONS
<br />ENTIRELY AT HIS/HER RISK. DECIDUOUS
<br />19, POTTED PLANTS: 4/1 - 6/1; 9/21 -
<br />11/1
<br />20. DECIDUOUS 7B&B: 4/1 - 6/1; 9/21 -
<br />11/1
<br />21. EVERGREEN POTTED PLANTS: 4/1 - 6/1; 9/21-11/1
<br />22. EVERGREEN B&B: 4/1 - 5/1; 9/21 -
<br />11/1 TURF/LAWN SEEDING: 4/1 - 6/1; 7/20
<br />- 9/20
<br />23. NATIVE MIX SEEDING: 4/1 - 7/20; 9/20-10/20
<br />24. MAINTENANCE SHALL BEGIN IMMEDIATELY AFTER EACH
<br />PORTION OF THE WORK IS IN PLACE. PLANT MATERIAL
<br />SHALL BE PROTECTED AND MAINTAINED UNTIL THE
<br />INSTALLATION OF THE PLANTS IS COMPLETE, INSPECTION
<br />HAS BEEN MADE, AND PLANTINGS ARE ACCEPTED
<br />EXCLUSIVE OF THE GUARANTEE. MAINTENANCE SHALL
<br />INCLUDE WATERING, CULTIVATING, MULCHING, REMOVAL OF
<br />DEAD MATERIALS, RE -SETTING PLANTS TO PROPER GRADE
<br />AND KEEPING PLANTS IN A PLUMB POSITION. AFTER
<br />ACCEPTANCE, THE OWNER SHALL ASSUME MAINTENANCE
<br />RESPONSIBILITIES. HOWEVER, THE CONTRACTOR SHALL
<br />CONTINUE TO BE RESPONSIBLE FOR KEEPING THE TREES
<br />PLUMB THROUGHOUT THE GUARANTEE PERIOD.
<br />25. ANY PLANT MATERIAL WHICH DIES, TURNS BROWN, OR
<br />DEFOLIATES (PRIOR TO TOTAL ACCEPTANCE OF THE
<br />WORK) SHALL BE PROMPTLY REMOVED FROM THE SITE
<br />AND REPLACED WITH MATERIAL OF THE SAME SPECIES,
<br />QUANTITY, AND SIZE AND MEETING ALL LANDSCAPE
<br />LEGEND SPECIFICATIONS.
<br />26. WATERING: MAINTAIN A WATERING SCHEDULE WHICH WILL
<br />THOROUGHLY WATER ALL PLANTS ONCE A WEEK. IN
<br />EXTREMELY HOT, DRY WEATHER, WATER MORE OFTEN AS
<br />REQUIRED BY INDICATIONS OF HEAT STRESS SUCH AS
<br />WILTING LEAVES. CHECK MOISTURE UNDER MULCH PRIOR
<br />TO WATERING TO DETERMINE NEED. CONTRACTOR SHALL
<br />MAKE THE NECESSARY ARRANGEMENTS FOR WATER.
<br />TURF NOTES:
<br />TURF ESTABLISHMENT SHALL BE ACCOMPLISHED IN
<br />ACCORDANCE WITH THE PROVISIONS OF THE MN/DOT 2105 AND
<br />2575 EXCEPT AS MODIFIED BELOW:
<br />1. ALL AREAS TO RECEIVE SOD SHALL ALSO RECEIVE 6" OF
<br />TOPSOIL PRIOR TO INSTALLING SOD. TOPSOIL SHALL BE FREE
<br />OFTREE ROOTS STUMPS BUILDING MATERIAL ANDTRASH
<br />AND SHALL BE FREE OF STONES LARGER THAN 1 }" INCHES IN
<br />ANY DIMENSION.
<br />2, WHERE SOD ABUTS PAVED SURFACES, FINISHED GRADE
<br />OF SOD/SEED SHALL BE HELD 1" BELOW SURFACE
<br />ELEVATION OF TRAIL, SLAB, CURB, ETC.
<br />3, SOD SHALL BE LAID PARALLEL TO THE CONTOURS AND
<br />SHALL HAVE STAGGERED JOINTS. ON SLOPES STEEPER
<br />THAN 3:1 OR IN DRAINAGE SWALES, SOD SHALL BE
<br />STAKED SECURELY.
<br />4. TURF ON ALL OTHER AREAS DISTURBED BY
<br />CONS RUCTION SHALL BE RES GRED BY SEEDING,
<br />MULCHING AND FERTILIZING. SEED MIXTURE NO.25-121
<br />(FORMERLY M,DOT 240) WILL BE PLACED AT THE RATE
<br />OF 70 POUNDS PER ACRE.
<br />5, ALL DISTURBED AREAS TO BE TURF SEEDED, ARE TO
<br />RECEIVE 4' TOP SOIL, SEED, MULCH, AND WATER UNTIL
<br />A HEALTHY STAND OF GRASS IS OBTAINED. FOR SLOPES
<br />STEEPER THAN 3:1 OR IN DRAINAGE SWALES INSTALL
<br />EROSION CONTROL BLANKET.
<br />5. ALL DISTURBED AREAS TO RECEIVE NATIVE WETLAND
<br />SEEDED, ARE TO RECEIVE ENGINEERED SOIL, SEED,
<br />MULCH, AND WATER UNTIL A HEALTHY STAND OF GRASS
<br />IS OBTAINED. FOR SLOPES STEEPER THAN 3:1 OR IN
<br />DRAINAGE SWALES INSTALL EROSION CONTROL BLANKET.
<br />DRY INFILTRATION PONDS:
<br />1. MIX 33-261 AT 82LBS/ACRE TO BE PLANTED IN THE
<br />POND BOTTOM AND UP 3 FEET FROM THE BOTTOM
<br />2, MIX 35-241 AT 84.5 LBS/ACRE TO BE PLANTED FROM
<br />THE 310 TO THE TOP OF POND
<br />3, FERTILIZE AT 10-10-20 AT 400 LBS/ACRE, MULCH TYPE
<br />3 AT 2 TONS/ACRE PLUS DISC ANCHORING
<br />4. USE BLANKET FOR AREAS OF CONCENTRATED FLOW,
<br />SUCH AS POND CORNERS OR AREAS WHERE DITCHES
<br />CARRY WATER INTO POND - WHEN USED FOR
<br />PRETREATMENT THE AREA MUST BE STAKED AND
<br />COMPACTION IS PROHIBITED
<br />WARRANTY PERIOD.
<br />F STAKING 15 REQUIRED BY SITE CONDITIONS,
<br />AROUNDCONTRACTOR
<br />THODIRI
<br />DUN
<br />01 TRMEH
<br />INOI CE
<br />.'A' TIEE TRU.11 "Ll APPROVAL BY
<br />LANDSCGPE
<br />T.
<br />DE&INSTRCALL RODENT PROTECTION,'
<br />UAR1111 RE CLOTH GHIN CILINDEN,�, CIA 11
<br />"'STILL TREE SUIT " "IT FLAIE V 11 11E ATTOP OF
<br />THE BERPT FAL, RV.VE '0 L N LEVEL MA NNE,
<br />REMOVE BURLAP, THINE, ROPE AND V11IRE
<br />HROI TOP HALF 11 111T BILL
<br />..,.
<br />DUTCH HNN H SA
<br />EDBUILD,
<br />D ooNDInONVAaITsucEa BEYOND
<br />�D
<br />R
<br />E x(11 a4'T cove PALTER BALE UNDISTURBED OR
<br />u JluBeanOE J CARITY BIND
<br />ID IT' OF TREE"E"' DSO rH SPADE BV HAND
<br />��.PLq�TO Rnv O'.ivITn PREvaRED saE
<br />N ING
<br />DEEPERTHAN ROOT anDIGPLANTINGPITP u of MI Da1111
<br />UNT HEIGHT AccoRDIND TO AnMI 1691 %
<br />TAMP 10 L AROUND ROIT BALL BASE FIREASIRITH -T
<br />�\ TREE PUANTIN6 DETAIL PRESSURE so THAT ROOT BALL DOES NOT
<br />SITrT
<br />i 1 I -E.1/1 -1 1
<br />THE ENTIRE BED INSTALL 2 LAfER
<br />T w/ """"E"�MULCH, Do NOT PwcE IN
<br />APPLY PRE ENSEILE.T
<br />11
<br />TEI
<br />EDGE CONDITION VAaIEs RODE
<br />�N AND SPECIFICATION
<br />4 HE
<br />CE
<br />DEEPERITI EAN
<br />Y iTHAI TOOT FALL HIT
<br />�""'IDES AND ""'I Or
<br />LADTNO BED. TH SPADE S
<br />�\
<br />SHRUB PLANTING DETAIL urvDlsruaBEO suBOanO
<br />1 1 I -E.1/1 -1 1
<br />Summary
<br />Revision History
<br />Certification
<br />Client
<br />Project
<br />Sheet Title
<br />Sheet No. Revision
<br />Sambatek
<br />A__
<br />o �e e sNbT �I,Ne
<br />.'�°
<br />�PeA ttRde.«el =odlo"oI Ie
<br />PAXMAR
<br />MISKE MEADOWS,
<br />PRELIMINARY LANDSCAPE
<br />Ph°rePA��M'I R�
<br />�� ��
<br />www.sambatek.com
<br />D-1:116/NRH
<br />�-
<br />ELK RIVER, MN
<br />DETAILS
<br />BookIIPE,
<br />Thal ssu .oEnsnm6
<br />�,�a�s�a�I
<br />Project No. PAX 20460
<br />Engineering l Surveying l Planning l Environmental
<br />"rePue4 med,S,M""gnl,, @
<br />
|