Laserfiche WebLink
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY <br /> COMMUTER RAIL SYSTEM - SERVICE CONCEPT B <br /> PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) <br /> SEGMENT H - BECKER TO CLEAR LAKE APPROX. LENGTH (MI): 7.0 <br /> <br /> COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL <br />COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS <br /> COST <br /> QUANTITY COST QUANTITY COST QUANTITY COST <br />STATION (CLEAR LAKE) <br />-"-P~_AT-F-O-FiM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 <br />TICKET VENDING MACHINE EA 115,000 2 230,000 <br />PUBLIC ADDRESS & VMS EA 105,000 2 210,000 ...... <br />SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000 <br />SURFACE PARKING SPACE 1,500 100 150,000 <br />PROPERTY ACQUISITION ACRE 100,000 1 100,000 <br />SUBTOTAL 1,540,000 <br />TRACKWORK <br />TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 <br />TURNOUT: #20 (NEW/UPGRADE) EA 170,000 <br />TURNOUT: #24 (NEW/UPGRADE) EA 185,000 <br />CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 <br />CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 <br />CROSSING SURFACE (NEW/UPGRADE) FT 675 <br />SUBTOTAL <br />CIVIL / STRUCTURES <br />EARTHWORK / STRUCTURES LS <br />MODIFY STRUCTURES LS <br />SUBTOTAL <br />SYSTEMS <br />.... ~I~i-ING/CTC (NEW/UPGRADE) MI 75,000 <br />CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 <br />CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 <br />CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 <br />CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 <br />SUBTOTAL <br />RIGHT-OF-WAY SF 4.00 <br />CONSTRUCTION SUBTOTAL 1,540,000 <br />ADD-ONS <br />ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 308,000 <br />CONTINGENCY (20%) 308,000 <br />TOTAL (1999 DOLLAR S) 2,156,000 <br /> <br />BRW, Inc. D [~ /~ E~ c~ Con-b-01.xls[SEGH] 12/03/98 <br /> <br /> <br />