Draft 9-3-14 <br /> DRAFT TIMELINE FOR PLANNING AND OPENING OF HOULTON PROPERTY <br /> 2014 <br /> Oct/Nov • Closing on acquisition of property <br /> Fall • Appointment of planning committee <br /> • Initial meetings with FMR <br /> • Initial meeting with DNR <br /> • Meeting with Anoka County to get their advice on management/planning <br /> 2015 <br /> Winter • Planning activities continue <br /> Spring • Planning activities continue <br /> Summer • Planning activities continue <br /> • Initial improvement activities commence (removal of house,etc.) <br /> Fall • Planning completed <br /> • First phase of restoration begins (buckthorn removal) <br /> • Initial improvement activities continue <br /> 2016 <br /> Winter • Initial improvement activities continue <br /> Spring • Initial improvements completed (parking,signage,etc.) <br /> • Land open to the public for hiking,etc. <br /> Summer • Second phase of restoration begins (prairie, if funding available) <br /> Fall • Land open to public hunting <br />